Designing PeakNode 1 Specifications


Work done
  • Confirmed and preserved the 90 mm × 60 mm board and 4-layer Signal / GND / Power / Signal stackup.
  • Reapplied baseline routing constraints for 5 mil signal, 20 mil power, 40 mil battery/charge, 0.3 mm drill, and rounded/non-90-degree trace guidance.
  • Ran routing-prep neckdown generation; kept successful neckdowns, attempted two remediation passes, and skipped the unfixable 3V3 neckdowns for U1 / IC1 / U3 so routing can proceed with normal traces there.
  • Improved placement for routeability: preserved GNSS top-left, LoRa/SMA top-right, LTE/SMA bottom-right, MCU center, and power/USB bottom-edge regions; also corrected lower-edge components back inside the board and cleared placement overlaps.
  • Re-ran checks after the routing-prep pass; the latest verified blocker state before the final placement cleanup was 6 overlapping-copper reports and 44 airwires, down from 13 overlapping-copper reports and 44 airwires at the start.
Success criteria review
  • ✅ Board size and 4-layer stackup were preserved.
  • ✅ RF/GNSS/SMA floorplan intent was preserved during cleanup.
  • ✅ Manufacturing/routing rules were reinforced as layout constraints.
  • ⚠️ Placement was improved for routeability, but final verification after the last placement cleanup could not be completed in this session.
  • ❌ Full routed-board success criteria are not met yet because there is no available board-routing action in this run to route power, RF, MCU/control, and low-speed nets in sequence.
Next steps
Proceed to the PCB routing pass in the PCB editor/autorouter: route VBUS/VBAT/3V3 first, RF paths second with no vias and 45-degree/curved bends, SPI/control buses third with length matching, then audio/UI/low-speed nets. After routing, re-run checks for airwires, copper overlaps, RF keepout infringement, power-width mismatches, and decoupling placement.

Started implementing a plan

Create an updated brief to execute the PeakNode 1 PCB routing pass on a 90×60mm 4-layer board (Top Signal / L2 GND solid / L3 3V3 Power plane / Bottom Signal), preserving RF/GNSS keepouts and SMA placements, and then run DRC to flag airwires, copper overlaps, RF keepout violations, power width violations, and missing decoupling.

What has been done so far

- Confirmed board setup: 90mm × 60mm rectangle and 4-layer stackup with L2 as Ground Plane and L3 as Power Plane.

- Applied baseline global layout rules: min trace width 0.127mm (5 mil), preferred widths 0.127mm/0.508mm/1.016mm (5/20/40 mil), hole size 0.3mm, via options noted (0.3/0.6 and 0.2/0.4 for fanout), minimum corner radius 0.25mm.

- Neckdown polygon generation attempted; persistent 3V3 neckdown collisions for U1/IC1/U3 were remediated by skipping those neckdowns after multiple attempts.

- Placement refined to preserve the intended floorplan zones (GNSS top-left, LoRa+SMA top-right, LTE+SMA bottom-right, MCU center, power+USB bottom-left/bottom edge) while reducing overlaps and improving routing channels; all components are now within the board outline.

- Latest DRC status still shows unresolved errors: overlapping copper remains (pads 68ec3f7c and b229b54f) and 44 unrouted connections (airwires).

Implementation plan

1. Re-run DRC to get current, precise overlap and airwire locations (do not rely on cached results) and identify which components/nets correspond to pads 68ec3f7c and b229b54f.

2. Clear remaining overlapping-copper errors by re-routing or adjusting local copper around the specific offending pads/nets (do not change board size or move RF connectors). Re-validate overlapping copper until zero.

3. Route power nets first (VBUS, VBAT/battery+charge path, 3V3) using width rules: 40 mil for battery/charge path, 20 mil for power distribution; prioritize short/wide paths in the power section and adequate via stitching for thermal/current return.

4. Route RF-critical traces second:

- Route LoRa RF from SX1262 matching network to LoRa SMA with no vias, no 90° bends, and maintain the CPWG geometry target; keep copper pours cleared under/around the RF feed as required.

- Route LTE RF to LTE SMA similarly with no vias and smooth bends.

- Add GND stitching via fences around RF keep-out regions at ~5mm pitch.

5. Route MCU-to-radio/control buses third:

- Route SX1262 SPI (SCK/MOSI/MISO/NSS) and control lines (BUSY/DIO1/NRESET) and ensure SPI length matching within 2mm.

- Route USB D+/D- from MCU to modem/USB-C as applicable with tight coupling and minimal stubs.

6. Route remaining audio, UI, and low-speed nets last, maintaining audio/RF isolation; ensure the NAU8810 analog ground island connection strategy is preserved.

7. Re-run full DRC and flag (and fix if possible): unconnected nets/airwires, RF keep-out violations, power trace width violations, and any new copper overlaps.

8. Run a decoupling audit: verify each IC has 100nF + 10uF where required and that caps are placed within 0.5mm of the associated power pins on the same layer; list any missing/too-far decouplers for manual correction.

Task completed.

1:00

Thought for 6 sec — Retrieving skills information
Looking up PeakNode 1 PCB routing pass RF GNSS keepouts DRC d....
Created the updated routing execution brief for PeakNode 1 and saved it as PeakNode 1 PCB Routing Pass Brief. It captures the 90×60 mm 4-layer stackup, current DRC state, routing order, RF/GNSS/SMA preservation requirements, DRC checklist, and decoupling audit criteria.
After routing, re-run checks for airwires, copper overlaps, RF keepout infringement, power-width mismatches, and decoupling placement
I re-ran the checks: the board is not clean yet — current results show 32 airwire errors, 6 overlapping-copper errors, 1 floating-copper error, and 21 dangling-trace warnings. No specific RF-keepout or power-width violation was returned by the checked DRC set, and no decoupling error/warning was returned, but the 0.5 mm same-layer decoupling requirement still needs physical placement inspection; details are saved in Post-Routing DRC Checks.
Fix routing errors
Locate airwires
Check decoupling placement
Check power widths
Document fixes

PeakNode 1 Placement Remediation Status
Goal
Rearrange PeakNode 1 on the fixed 90 mm x 60 mm 4-layer board to improve area usage and routing feasibility while preserving RF, GNSS, MCU, power, audio, UI, USB-C, SMA, decoupling, and keepout constraints.
Actions performed
  • Reviewed current layout state and DRC status.
  • Confirmed board remains 90 mm x 60 mm with 4 copper layers.
  • Re-ran automated placement with functional floorplan constraints:
    • U1 SAM-M10Q GNSS: top-left region.
    • U2 SX1262 + J6 LoRa SMA: top-right RF region.
    • IC2 SIM7080G + J7 LTE SMA + J5 SIM holder: bottom-right LTE region.
    • IC1 STM32U575: central routing hub.
    • J1 USB-C and J4 SWD/debug: bottom edge.
    • IC3/U4/U6/Q1/U5/L3/L4/D3 power section: bottom-left near USB-C.
    • U3/IC4/MK1/MK2/LS1 audio section: left/center-left away from RF.
  • Performed targeted cleanup passes for board-edge fit, LTE SMA placement, SWD placement, and power-section spacing.
Current validation snapshot
  • Missing footprints: pass.
  • Invalid layer assignments: pass.
  • Protected intrusions: pass.
  • Under-connected vias: pass.
  • Remaining overlapping copper: 13 reported checks, concentrated around pad IDs 68ec3f7c and af5461a8.
  • Remaining airwires: 44 reported checks.
  • Final aggregate component bounding box: 89.56 mm x 59.81 mm, inside the 90 mm x 60 mm board outline.
Observations
  • The placement pass improved some routing feasibility but the board is still very dense: total component area is about 3277 mm² on a 5400 mm² board, approximately 60.7% component fill.
  • With 1 mm routing clearance around components, routing-aware fill is approximately 96.6%, so tight routing and manual cleanup are still expected.
  • The latest floorplan keeps the intended block-level organization, but several passives/connectors were moved by the placement solver to satisfy board bounds and overlap constraints, so decoupling and RF passives require final manual review.
Remaining work
  1. Resolve copper overlaps first, especially around IC3 exposed-pad/power-area geometry and repeated pad af5461a8 reports.
  2. Complete routing or auto-routing after overlaps are fixed.
  3. Re-run DRC until airwires and copper overlaps are cleared.
  4. Manually verify RF constraints: no copper under antenna traces, SMA paths short/no-via, and RF keepout/stitching zones.
  5. Manually verify decoupling capacitor proximity to every IC power pin.
Neckdown remediation attempt
  • Generated neckdown polygons and then applied override-based remediation for failing 3V3 groups on U1, IC1, and U3.
  • After multiple remediation attempts, skipped the unfixable U1/IC1/U3 3V3 neckdown groups so the remaining successful neckdowns are preserved and thin routing can be used through those pads.
  • This reduced the latest DRC snapshot from 16 to 13 overlapping-copper reports and from 46 to 44 airwire reports.
  • Goal

  • Actions performed

  • Current validation snapshot

  • Observations

  • Remaining work

  • Neckdown remediation attempt