Rev.17 Board Bring-Up Plan
Gate 0 — before assembly
  • Freeze exact LPDDR4/eMMC MPNs and validate footprint, IBIS/timing and rail currents.
  • Complete i.MX 8M Mini IOMUX table, PMIC handshake, boot straps and DDR/eMMC configuration.
  • Verify six-layer fabrication stack and controlled-impedance coupons.
  • Verify every connector footprint/orientation against vendor drawings.
Stage 1 — unpowered checks
  • Inspect BGA alignment and shorts; measure resistance to GND on VSYS, all PMIC rails, RF_RAIL and display rails.
  • Confirm no wired dock pin is connected to charging power.
Stage 2 — battery/charger path
  • Current-limit the battery simulator. Validate DW01A/FS8205A polarity and cutoff behavior.
  • Validate BQ51013B output under aligned Qi transmitter; then BQ25895 VSYS, charge current, thermistor and protection settings.
  • Harvesters are tested independently and must not back-power one another.
Stage 3 — PMIC sequence
  • Scope LDO1, LDO2/RTC, BUCK1+BUCK5+LDO4, BUCK2+LDO3, BUCK7, BUCK8, BUCK6, LDO6, then POR_B.
  • Verify PMIC_ON_REQ, PMIC_STBY_REQ, RTC_RESET_B, WDOG_B, IRQ_B and I²C.
  • Confirm BSP incorporates NXP CIN 202005006IU01 handling for LDO1/LDO2.
Stage 4 — clocks, reset and boot
  • Verify 24 MHz clock amplitude/startup and 32.768 kHz source.
  • Confirm boot straps and recovery path; attach JTAG and halt A53/M4.
  • Boot from eMMC; run DDR training and memory stress before enabling radios/displays.
Stage 5 — interfaces
  • Enumerate dock native USB2 in device mode; verify no VBUS charging path.
  • Enumerate BG95 over dedicated native USB2 and run UART AT-command test.
  • Test MIPI head detect/ID before enabling display rails; validate each display variant separately.
  • Test nRF5340 UART, PN7160 I²C, AD5940 SPI and sensor buses.
  • Prove emergency input wakes the M4 from deepest supported state while Linux is stopped.
Stage 6 — RF and peak load
  • Validate BG95 2.7 A EGPRS burst with rail droop, PMIC/charger/battery temperature and reset monitoring.
  • Perform LTE/GNSS conducted tests before antenna OTA/tuning work.
Pass criteria
No unexpected rail sequence, brownout, thermal limit, USB role conflict, memory error, or shared emergency GPIO. Record oscilloscope captures and measured sleep/typical/peak currents in the power-budget file.
  • Gate 0 — before assembly

  • Stage 1 — unpowered checks

  • Stage 2 — battery/charger path

  • Stage 3 — PMIC sequence

  • Stage 4 — clocks, reset and boot

  • Stage 5 — interfaces

  • Stage 6 — RF and peak load

  • Pass criteria