Bring-Up Plan
Analog validation checkpoint — 2026-10-10
Analog is now wired but unplaced/unrouted, superseding the analog-unbuilt statement below. Before any analog bench operation, repair/qualify stored ADC capacitor charge during rail collapse and source sequencing; no live sources during transitions. Complete source current budgets, passive MPNs and layout verification first. J46/J47=A1–4, J48/J49=B1–4; each pin1 odd channel,pin2GND,pin3 even channel. Confirm independent buses,0x48 ADCs and0x41 limits; verify divider/switch orientation and100 nF bypass/filter connectivity. After hardware gate closes, start clean common-ground low-current0 V source with stable local3.3 V, then sweep3.3/5/10 V only for selected application ranges. Expected passive endpoints0.591896/0.896813/1.793625 V are model baselines, not precision acceptance bounds. Log source impedance, active loading, calibration, rail ramp/off-state voltages and currents across temperature with a safe qualification fixture. Do not inject negative,12/24 V, raw automotive or ESD signals without engineered test protection. No motor bring-up; motor unbuilt. Latest ERC30 U5/U6 Errors/6 diode metadata Warnings remains open. See analog-expansion-checkpoint.
Added expansion validation — 2026-10-10
New circuitry is unplaced/unrouted and must pass the separate layout checkpoint before assembly. Inspect J42/J43 pin1 current-limited3V3,2GND,3GPIO39,4GPIO40,5SDA,6SCL; verify its power load plus J18/J37 remains≤90 mA per domain. For J44/J45, pins1/2=LIM1/GND,3/4=LIM2/GND,5/6NC. Verify U10/U11 local rail and100nF bypass, I2C0x41 responds on the correct bus only, IO0/IO1 inputs and IO2/IO3NC. With low-current logic bench power, measure open near3.3 V and closed below the verified LOW threshold on each input; check NO/NC interpretation, contact resistance, debounce and bus-failure inhibit behavior. Confirm D25–D28 orientation: pin1GND,2local3V3,3filtered input. Do not inject12 V, motor power, powered sensor signals or off-state voltages into limits. ESD residual clamp, rail injection/absorption and full-temperature performance are not qualified. No motor or analog bring-up is possible because those circuits are not installed. See stepstick-expansion-decision-gate for item-level unfinished scope.
Revised continuous-load ceilings — 2026-10-08
1 A EACH on all eight outputs, 4 A load per bank, 8 A aggregate load, plus actual switch/support currents. Supersedes earlier 2 A-channel/8 A-bank/16 A-return limits. Firmware/external loads must comply; VNQ is not a precision1 A limiter and diagnostics are not MCU-readable. Independent external branch/bank protection, characterized inrush and inductive suppression remain required. Start unloaded/low limit; increment one output, four/bank, then both only after interim temperature/drop and current-path evidence. These ceilings are not released ratings. revised-current-path-review records current individually blocked paths; no export while power/via/mount blockers remain.
Bench prototype boundary
Use current-limited regulated5 V and separate positive9–16 V bench bank supplies only. J3 source capability≥3 A after derating; this is not the initial current-limit setting. External bank and per-output branch protection is required and NOT installed on the carrier. Direct battery prohibited. See bench-assembly-evidence for connector drawings, budgets and exact recovery limitations. Routing/DRC/manufacturing verification is a separate lead gate; closed-enclosure thermal tests occur after prototype fabrication.
Staged first assembly
- With all power and removable boards absent, check shorts, component polarity and soldering. Dev-board2.54 mm pitch/25.4 mm row spacing and photo map are verified inputs; continuity now verifies assembly, not a demand for an existing prototype before fabrication.
- Verify J1/J21 pin21 is5VIN, pin22GND, pins01/02 local3V3; J2/J22 pins01/21/22GND. Check all used contacts against
esp32-socket-pin-map. Check J18/J37 pad1 supply,2SDA,3SCL,4GND and spare terminals1local3V3,2GPIO39,3GPIO40,4GND.
- Start J3 at5 V with a low current limit and both boards removed; investigate unexpected current before increasing limit. Local3V3 is supplied by removable boards and must not be expected with them absent. Test each board separately, then insert with power OFF and raise current limit in stages for one then both boards. Planning allowance0.8 A/board inclusive of exported3V3 loads,0.4 A other carrier loads,2 A operating budget within3 A source capability; actual peaks and regulator spare capacity are measured, not guaranteed. Each sensor≤90 mA; exported3V3 total≤0.2 A/board planning allowance.
- Remove corresponding J19/J23 link before USB power; no automatic source ORing. Check rails and droop during boot/radio activity. No external data/sensor backpower while carrier supply is off.
- Verify AHCT inputs/outputs deterministic and disabled during boot/removal. Verify U9 only on MCU A I2C and independent sensor buses/current limits. Start100 kHz.
- Bring accessory CAN up listen-only with exactly the required two physical end terminations across complete harness. GPIO18 HIGH standby until configured.
- Test trigger inputs from fused/current-limited bench12 V with controlled polarity/threshold tests. Do not inject undefined vehicle surges.
- Bring one bank up unloaded at9–16 V with low current limit and installed external bank/branch protection. Scope VNQ INPUT HIGH≥2.1 V/LOW≤0.9 V, SEL/SEn LOW, FaultRST HIGH. Test each output at small current before increasing load; log connector/VNQ temperature and rail droop. Confirm GPIO39/40 paths/100 Ω continuity.
- Measure biased effective capacitance/load-step response. Nominal47 µF is not a guaranteed biased value. Test one channel, then four/bank, then both banks only after routed-current paths, harness ampacity/fuse inrush/ambient coordination and intermediate temperatures are acceptable.
Fault and controlled restart
FaultRST is only pulled HIGH; no software reset path exists. INPUT LOW means OFF, not guaranteed fault unlatch. On operator-observed/application-reported fault: latch SAFE, set all affected-bank commands LOW, turn external bank OFF, isolate fault/load, cool and verify discharge/no backfeed. Remove applicable power, then restart logic first with all commands LOW and FaultRST measured HIGH; restore bank last at low current limit with safe/unloaded load. Validate this power-cycle restart experimentally; datasheet does not establish its latch-reset timing. If still latched, STOP. A specified FaultRST LOW pulse needs separately engineered reset access/fixture; firmware cannot supply it. Do not short energized pins or continually retry. Diagnostics are disabled/not MCU-readable, so firmware has no automatic VNQ fault detection claim.
Post-fabrication qualification
Assembled socket continuity, exact dev-board peak consumption/regulator margin, low-power restart and biased capacitor tests precede higher-load operation. Full-load closed-enclosure thermal at1 A/channel,4 A load/bank and any real8 A aggregate bottleneck plus support currents, vibration/connector retention and automotive surge/EMC tests are post-fab release gates for vehicle/full-load use, not prerequisites requiring a prototype before prototype fabrication. Provisional dev-board envelope, USB/IPEX/removal and3D source uncertainty remain disclosed fit limits.