| Deliverable | Purpose | Output file/status |
|---|---|---|
| Engineering Review Report | Challenge complete architecture and major design choices. | Pending |
| Updated Architecture Recommendations | State keep/change/remove decisions for each subsystem. | Pending |
| Power-State Diagram | Define Off, USB connected, Charging, Idle, Paired, Streaming, Low battery, Sleep, Shutdown. | Pending |
| System Block Diagram | Concise audio and power diagrams. | Included in ERS; may be expanded in review. |
| Component Comparison Matrix | Compare RF module, codec, mic preamp, line driver, charger, fuel gauge, regulators. | Pending |
| Risk Register | Track RF, audio, power, manufacturing, compliance, and service risks. | ERS has initial risk table; expanded register pending. |
| Prioritized Design Change List | High / Medium / Low schematic and documentation changes. | Pending |
| Updated Production Readiness Checklist | Define exactly what blocks production intent. | Pending |
Table
| Subsystem | Current Rev A choice | Review questions |
|---|---|---|
| RF module | RTX1090R1 provisional | Confirm lifecycle, price, availability, SDK, licensing, reference layout, antenna, and exact codec interface. |
| Microphone preamp | THAT1580 | Compare THAT1580, THAT1512, INA217-class, INA333, and other pro mic preamps. |
| Codec / ADC / DAC | TLV320AIC3204 | Compare TI, Cirrus Logic, Analog Devices, AKM, ESS options for latency, SNR, control, package, supply, availability. |
| Balanced output | THAT1646 | Confirm output level, headroom, supply rails, noise, mixer compatibility, protection. |
| Charger / power path | BQ24074 | Check heat, power-state behavior, USB behavior, RF/audio noise, simplification options. |
| Fuel gauge | MAX17048 | Decide keep/remove based on UX and firmware ownership. |
| Regulators / rails | AP2112K 3.3 V, TPS65131 ±5 V | Review efficiency, noise, component count, and alternatives. |
| USB-C | Charging-only with protected D+/D− | Decide whether USB data/debug/update is required. |
| Clocking | Provisional RF/codec mapping | Define clock master/slave, sample rate, jitter risk, and exact Sheerlink requirements. |
| Power distribution | Separate TX/RX rails | Review current draw, load margins, startup sequencing, and ERC missing-power findings. |
Status
Baseline
Objective
Required Deliverables
Review Scope by Subsystem
Immediate Known Review Issues
Next Recommended Work Order