Project Startup Help

They’re still running. I’ll check final status once more and then give you the project links and current state so you’re not blocked waiting.
Created two separate PCB projects and started the split/place work in each:
Current status:
  • TX clone: RX circuitry removed, board-mounted XLR replaced with compact XLR harness pads, 25 × 80 mm / 4-layer target set, placement still running.
  • RX clone: TX circuitry removed, board-mounted XLR replaced with compact XLR harness pads, 25 mm width / 4-layer target set, placement still running.
  • Master project remains unchanged as the system/reference design.
Open item:
  • Both split-placement tasks are still running; they exceeded the wait window but are actively working on non-RF placement and verification.
Next step:
  • Open each project link later to review the completed thread result, or ask me to check their status again.
Check split projects
Check TX status
Check RX status
Fix failed split tasks
Compare split BOMs

Refine this doc
Ask about this doc
Phase 2 Engineering Review Plan — Munkrofon
Status
Active review plan. No PCB placement or routing should begin until the review deliverables below are complete, unless a review identifies a necessary schematic correction.
Baseline
Objective
Move Munkrofon from exploratory prototype toward engineering-quality prototype by validating, challenging, and improving the existing architecture without restarting from scratch.
Optimization priority:
  1. Reliability
  2. Audio performance
  3. RF performance
  4. Manufacturability
  5. Serviceability
  6. Battery runtime
Required Deliverables

Table


DeliverablePurposeOutput file/status
Engineering Review ReportChallenge complete architecture and major design choices.Pending
Updated Architecture RecommendationsState keep/change/remove decisions for each subsystem.Pending
Power-State DiagramDefine Off, USB connected, Charging, Idle, Paired, Streaming, Low battery, Sleep, Shutdown.Pending
System Block DiagramConcise audio and power diagrams.Included in ERS; may be expanded in review.
Component Comparison MatrixCompare RF module, codec, mic preamp, line driver, charger, fuel gauge, regulators.Pending
Risk RegisterTrack RF, audio, power, manufacturing, compliance, and service risks.ERS has initial risk table; expanded register pending.
Prioritized Design Change ListHigh / Medium / Low schematic and documentation changes.Pending
Updated Production Readiness ChecklistDefine exactly what blocks production intent.Pending
Review Scope by Subsystem

Table


SubsystemCurrent Rev A choiceReview questions
RF moduleRTX1090R1 provisionalConfirm lifecycle, price, availability, SDK, licensing, reference layout, antenna, and exact codec interface.
Microphone preampTHAT1580Compare THAT1580, THAT1512, INA217-class, INA333, and other pro mic preamps.
Codec / ADC / DACTLV320AIC3204Compare TI, Cirrus Logic, Analog Devices, AKM, ESS options for latency, SNR, control, package, supply, availability.
Balanced outputTHAT1646Confirm output level, headroom, supply rails, noise, mixer compatibility, protection.
Charger / power pathBQ24074Check heat, power-state behavior, USB behavior, RF/audio noise, simplification options.
Fuel gaugeMAX17048Decide keep/remove based on UX and firmware ownership.
Regulators / railsAP2112K 3.3 V, TPS65131 ±5 VReview efficiency, noise, component count, and alternatives.
USB-CCharging-only with protected D+/D−Decide whether USB data/debug/update is required.
ClockingProvisional RF/codec mappingDefine clock master/slave, sample rate, jitter risk, and exact Sheerlink requirements.
Power distributionSeparate TX/RX railsReview current draw, load margins, startup sequencing, and ERC missing-power findings.
Immediate Known Review Issues
  • RTX1090R1 public datasheet does not publish exact Sheerlink codec pin mapping.
  • Antenna placeholders AE1–AE4 are not production antenna layouts.
  • Remaining ERC missing-power findings need formal classification before next schematic revision.
  • ±5 V split rails may be oversized/noisy/inefficient for final design but are justified by current audio IC choices.
  • MAX17048 fuel gauge may be unnecessary if simple battery indication is enough.
  • XLR input/output protection against RFI, ESD, and phantom-power abuse needs a dedicated review.
  1. Architecture and component review report.
  2. Power-state diagram and updated power budget using RTX1090 public current data.
  3. Codec/preamp/line-driver comparison matrix.
  4. Risk register and prioritized design-change list.
  5. Apply necessary schematic corrections.
  6. Only then proceed to schematic cleanup, board outline, stackup, placement, and routing.
  • Status

  • Baseline

  • Objective

  • Required Deliverables

  • Review Scope by Subsystem

  • Immediate Known Review Issues

  • Next Recommended Work Order