BOM Supply Audit


Check the availability and lead times for all components in this project. Flag any parts that are out of stock, have long lead times, or are approaching end-of-life. Suggest drop-in replacements for any at-risk components.
I’ll audit the BOM by manufacturer part number, check current distributor availability, lead times, and lifecycle status, then identify footprint- and function-compatible alternatives for any supply risks.
Availability audit started and the full 177-component BOM was normalized into 20 unique part types. Distributor data indicates good stock for ESP32-C3-WROOM-02-N4, V275LA10P, 74AHCT1G125W5-7, IRM-10-5, AO3400A, 282837-2, LEDs, and switch; LMR33630BDDAR is currently concentrated at LCSC, while PMS5003 and MQ-135 lack verified authorized-distributor availability.
The audit remains incomplete: detailed lead-time/EOL verification, generic passive specification checks, and validated drop-in alternatives could not be finished because no ACUs remain available. No project changes were made.
Check U2 availability
Review missing MPNs
Search sensor availability
Find LMR33630 alternatives
Rank sourcing risks

Waiting for input


No schematic drawn yet

Your and are available in the table tabs. Ask Flux to draw the schematic, or draw it yourself.

Board Bring-Up Plan
  1. Unpowered safety inspection: verify primary/SELV spacing, no copper bridge, fuse/MOV/module orientation, enclosure barriers. Do not energize an unenclosed board on an open bench.
  2. Use an isolation transformer, RCD/GFCI, current-limited source where appropriate, insulated fixture, PPE, and qualified personnel.
  3. First energize without MCU/sensors if assembly permits. Confirm 5V_SELV = 4.5-5.5 V and no continuity from primary to SELV.
  4. Confirm 3V3_SELV = 3.20-3.40 V; inspect buck SW, ripple, startup, regulator temperature.
  5. Fit MCU; verify EN reset, UART boot with GPIO9 low, flash test firmware, join Wi-Fi, and measure peak rail droop.
  6. Fit PMS5003; verify 9600 8N1 frames/checksum and >=30 s stabilization after wake.
  7. Fit MQ-135; verify heater current =24 h initial preheat before baseline characterization.
  8. Test both RGB LEDs at limited then full commanded brightness; verify level shifter and data chain.
  9. Thermal soak at worst enclosure ambient and simultaneous Wi-Fi TX/heater/PM/LED load. Pass if rails remain in tolerance and component/enclosure temperatures meet safety limits.
  10. Conduct hipot, leakage, protective impedance, abnormal operation, EMC pre-scan, surge/EFT, and production test development through qualified labs.