Project Start Query


The builder completed the risk-reduction changes and documentation. I’m doing the required independent read-only review now; after that we are at the schematic-completion checkpoint, with visual schematic cleanup as the only known unfinished item before layout.
Thought for 54 sec
Thought for 37 sec
"Kinethic Band Phase 1" completed.
Thought for 1 min 22 sec
Thought for 18 sec
Awaiting 1 background task
"Kinethic Band Review" completed.
The Phase 1 schematic and engineering package were substantially completed:
  • Expanded to 78 components and 42 nets
  • Added independent battery-temperature telemetry
  • Corrected the bulk capacitor, regulator inductor, and motor-connector selections
  • Selected low-cost JYC1027 ERM motors
  • Updated the power budget, BLE protocol, BOM, firmware starter, and bring-up plan
  • Added wireless compliance, safety-analysis, and preliminary FMEA files
  • Builder checks reported no electrical, passive, system, or schematic-legibility errors or warnings
The independent review executor finished, but I could not retrieve and reconcile its final findings. The schematic also remains visually crowded; electrical connectivity is complete, but functional-block organization still needs improvement before PCB layout.
We are effectively at the schematic-completion checkpoint, pending:
  • Reconcile the independent review findings
  • Apply any required corrections
  • Clean up the schematic canvas
  • Obtain your approval before PCB placement and routing
Execution stopped because your ACUs ran out.

Waiting for input


Preliminary FMEA
Scales: Severity (S), Occurrence (O), Detection (D), 1–10; preliminary RPN = S×O×D. Re-score after first-article evidence.

Table


Failure modeEffectExisting controlsSODRPNRequired action
Motor stuck on from firmware faultPain, heat, battery drainGate pulldowns, 2 s max-on, watchdog, disconnect timeout83372Verify watchdog-start ordering and hardware reset gate-low behavior
AO3400A drain-source shortOne motor continuously poweredFirmware cannot stop hardware short827112Measure fault current/temperature; consider per-channel series PTC or high-side disconnect in later revision
Four motors enabled accidentallyBrownout, cell protection trip, heatFirmware one-at-a-time policy, 1 A cell target, bulk capacitance73363Run bounded four-channel fault test and log minimum rails/current
Battery overcharge or charger faultFire/ventingProtected pack, BQ24074 regulation, TH1 TS, 300 mA setting102480Supplier qualification, charge-limit/termination testing, single-fault review
TH1 detached/open/shortCharging disabled or unsafe qualification responseIC1 TS hardware monitoring93381Mechanical bonding control and end-of-line hot/cold resistance test
TH2 detached/open/shortWrong telemetry/thermal lockoutIndependent ADC plausibility checks; TH1 unaffected63236Detect rail endpoints, set fault, stop haptics, inspect bonding
Battery connector reversedDamage or no operationControlled pack polarity and incoming inspection92472Keyed approved pack, polarity fixture, conspicuous assembly marking
Dock polarity reversedNo charge/damageD1 reverse-polarity series diode, keyed mechanics73242Verify worst-case reverse application and contact labeling
Pogo contact short/debris/corrosionHeating, intermittent chargeInput limit, ESD, splash-resistant direction745140Add dock overcurrent source protection, sweat/corrosion and debris testing
C13 installed reversed or surge failureRail short, heatingPolarized footprint and assembly inspection72456Add polarity mark/AOI rule; evaluate polymer alternative after transient test
L3 saturates/overheats3V3 collapse, reset, excess heat1.5 µH specified; TI requires 20% saturation margin over calculated peak735105Measure inductor current and temperature at 3.0 V input/worst load
Skin sensor reads low or loses contactMissed hot-surface conditionSensor plausibility, ambient/battery sensors, firmware lockouts835120Mechanical contact validation and fault injection
BLE stale/invalid commandWrong or prolonged cueCRC, sequence rules, 750 ms expiry, explicit STOP64248Protocol fuzzing and Android reconnect tests
H2/H4 wrist mapping wrongMisleading directional cueStored wrist side, deterministic transform, startup validation73363Human-factors test and visible orientation marking
Antenna detuned by enclosure/battery/magnetPoor link, disconnectsIntegrated antenna and keepout requirement545100Final enclosure RF range and radiated testing
Enclosure leaks sweat/waterCorrosion, shorts, skin hazardSplash-resistant design direction only846192Define IP target, gasket/vent design, artificial-sweat and ingress testing
Highest-priority actions
  1. Enclosure ingress/artificial-sweat validation.
  2. Dock debris/corrosion/overcurrent validation.
  3. Skin-sensor mechanical contact and fault detection.
  4. L3 peak-current/thermal validation.
  5. Hardware response to a shorted motor MOSFET; consider a future common motor-rail disconnect if residual risk is unacceptable.
This is a preliminary engineering FMEA, not a completed safety case or regulatory risk file.
  • Highest-priority actions