Drone Autonomy Spec


I’ll create a structured takeover report covering both boards, architecture, completed work, current live state, known blockers, recovery history, verification gates, and the exact order a new engineer should follow.
Created a project doc

PCB Engineering Takeover Report

View Document

PCB Engineering Takeover Report 1. Purpose and release status
This is the engineering handoff for the two-board KRYSTAL drone companion system. It consolidates the design intent, current implementation, known defects, routing history, verification evidence, and the recommended recovery sequence.
Current release status: HOLD — neither board is approved for fabrication or flight.
The next engineer should treat all counts in this report as the last confirmed state and rerun live ERC/DRC/layout checks before making changes. Do not generate Gerbers until every release gate in Section 13 passes.
2. Projects Safety / power / I/O base board
Created the comprehensive PCB Engineering Takeover Report.
It covers:
  • Both project links and board responsibilities
  • Current CM5 and S32K344 architecture
  • Power, camera, radar, autopilot, Wi‑Fi, FHSS and SIYI interfaces
  • Board dimensions, stackups and enclosure direction
  • Completed fixes and verified checks
  • Routing-service failure and recovery history
  • Known footprints, software and regulatory risks
  • Recommended takeover sequence
  • Fabrication-release gates
  • Immediate first-day checklist and required engineer deliverables
The report clearly marks both boards HOLD for fabrication until routing, interface freeze, DRC, thermal, software and mechanical validation are complete.
Review takeover report
Audit live board states
Prepare migration package
Freeze external interfaces

KRYSTAL Two-Board Sealed Enclosure Concept
Status: Mechanical concept for packaging and passive-cooling study; connector cutouts and final thermal qualification require the selected parts' mechanical drawings, loss maps, aircraft airflow data, and test results.
Design basis: Two stacked 110 × 110 mm PCBs on a 100 × 100 mm mounting-hole pattern, approximately 32.5 W conservative peak electronics dissipation, drone installation, rain/humidity/vibration exposure, serviceable screwed lid, and external XY target near 122 × 122 mm.
Current Flux PCB layout is 80 × 100 mm with a 1.30 mm stackup. This concept intentionally follows the requested future two-board 110 × 110 mm stack, not the present single-board outline. Final CAD must be regenerated from the released outlines, the specified 100 × 100 mm mounting pattern, connector models, SOM drawing, and antenna locations.
Use a two-piece machined or die-cast aluminum enclosure with a gasketed top lid:
  • Base: deep tray carrying both PCBs, perimeter gasket land, six lid screws, internal mounting pillars, external drone mounting lugs, and the primary heat-spreading wall.
  • Lid: aluminum heat-spreader plate with integral shallow external fins. The compute/SOM thermal stack should conduct directly to this lid.
  • Material: 6061-T6 CNC-machined aluminum for prototypes/low volume; transition to ADC12/A380 die-cast aluminum after geometry stabilizes. Use chromate conversion or hard anodize selectively, while leaving designated grounding and thermal-interface areas conductive.
  • Nominal walls: 2.5 mm CNC; 2.5–3.0 mm cast, with 1–2° draft for casting. Base floor and heat-spreader lid locally 3.0 mm minimum.
  • Corners: 5 mm external radius; ≥2 mm internal tool radius for CNC.
Aluminum is preferred over an all-polymer shell because rejecting approximately 30–35 W passively from a compact sealed volume requires a low-resistance conduction path and useful external radiating area. Polymer may still be used as a local RF window.
2. Proposed dimensions and stack-up
External envelope

Table


FeatureProposed dimension
Main housing plan size122 × 122 mm exact recommended body plan
Sealed body height, including compressed gasket46 mm nominal
Lid fin height above body5.5 mm nominal; 6.0 mm maximum
Fin fieldApproximately 96 × 98 mm, centered but divided into compute and power thermal zones
Exact recommended sealed body122 × 122 × 46 mm including compressed gasket
Maximum overall finned envelope122 × 122 × 52 mm maximum (51.5 mm nominal)
Mounting lugsPrefer below or within the 122 mm plan; if external, allow approximately 134–138 mm across lugs and treat that as a separate aircraft-interface envelope
Internal cavity and PCB clearances

Table


FeatureProposed dimension / clearance
Clear cavity XY inside nominal walls116.5 × 116.5 mm minimum
PCB edge clearance3.25 mm nominal per side, 2.5 mm absolute minimum away from walls; ≥4 mm near harness bends or RF coax
Board mounting-hole pattern100 × 100 mm square, centered on each 110 × 110 mm PCB; hole centers are 5.0 mm from each board edge
Nominal mounting-hole coordinatesRelative to board center: (±50.0, ±50.0) mm; relative to a lower-left board datum: (5,5), (105,5), (105,105), (5,105) mm
PCB thickness basisUse 1.6 mm nominal per board for mechanical concept; update to released stackups (current base-board stackup is 1.30 mm)
Lower PCB underside clearance4.0 mm from component envelope to base floor; increase where bottom-side connectors/components require it
Board mounting-plane separation18 mm nominal, adjustable with 16/18/20 mm spacers after SOM and mezzanine connector drawings are frozen
Inter-board component envelopeReserve 14.5 mm clear between a 1.6 mm lower board and the upper board underside at 18 mm plane spacing
Upper PCB top component envelope8.0 mm nominal outside the SOM/heat-spreader zone
Upper board to lid inner face10–12 mm nominal, consumed locally by SOM, spreader, and thermal pad
Keepout around enclosure pillars≥1.5 mm copper/component clearance beyond pillar diameter; confirm creepage and vibration needs
Height derivation
A realistic compact height is derived as follows rather than assuming an arbitrary box depth:
  • Base floor: 3.0 mm.
  • Lower-board underside hardware/air gap: 4.0 mm.
  • Lower PCB: 1.6 mm mechanical basis.
  • Board mounting-plane separation: 18.0 mm.
  • Upper PCB: 1.6 mm.
  • Upper component/SOM and spreader allowance: 8–10 mm typical concept envelope.
  • Compressible thermal pad tolerance: 1.0–1.5 mm compressed.
  • Lid plate: 3.0 mm.
  • Gasket/seam contribution and assembly tolerance: approximately 1–2 mm.
This produces a 43–47 mm sealed body, so 46 mm is the recommended nominal. External fins bring the practical maximum to approximately 52 mm. The 18 mm board spacing is a mechanical target, not a released dimension: verify it against the exact board-to-board connector mated height, SOM/component maximum Z, and cable access before fabrication.
3. Lid joint, gasket, and fasteners
  • Use a continuous tongue-and-groove perimeter joint outside the electronics cavity. The tongue provides shear registration so screws do not carry lateral vibration loads.
  • Preferred seal: one-piece closed-cell silicone foam gasket, 1.5–2.0 mm uncompressed, approximately 20–30% compression. For repeated servicing and stronger IP67 intent, use a molded silicone O-ring instead.
  • O-ring concept: 2.0 mm cross-section silicone, 50–60 Shore A. Machine a rectangular groove approximately 2.2–2.4 mm wide and 1.45–1.55 mm deep, then finalize from the selected O-ring supplier's gland table. Target 20–25% squeeze and avoid >85% gland fill across temperature/tolerance.
  • Provide a flat sealing land at least 3.5–4.0 mm wide around the groove, with no parting-line steps, tool witness marks, or fastener holes crossing the seal.
  • Use six M3 stainless screws: four corners plus one centered on each of two opposite sides. Keep adjacent fasteners approximately 45–55 mm apart; increase to eight screws if pressure testing shows excessive lid bow.
  • Use stainless helicoils or replaceable threaded inserts in aluminum rather than repeated screw engagement in soft cast metal. Add insulating anti-galling compound compatible with the coating.
  • Suggested M3 lid torque starts at 0.6–0.8 N·m, but must be validated against gasket compression, insert type, lid flatness, and fastener grade.
  • Add two 3 mm dowel/registration features or a full perimeter tongue to prevent gasket scrubbing during assembly.
4. Thermal management for approximately 32.5 W peak
Required heat path
The enclosure must be treated as the heat sink, not as a sealed air box:
  1. Locate the industrial i.MX8M Plus SOM and its highest-loss regulators on the upper PCB facing the lid.
  2. Use the SOM vendor's permitted contact region and maximum mechanical load; do not press on memory or unsupported packages.
  3. Couple the SOM shield/processor heat spreader to a 2–3 mm aluminum or copper spreader plate using a compliant gap pad.
  4. Couple that spreader to the lid with a 1.0–1.5 mm compressed, 3–6 W/m·K silicone gap pad. Design pad compression stops so vibration or screw torque cannot overload the SOM.
  5. Couple lower-board hot spots such as eFuses and power converters to the base using local thermal pads and a bolted aluminum bridge only after confirming component case contact is allowed. Otherwise use heavy PCB copper and thermal vias into standoff-adjacent heat-spreading regions.
  6. Keep the thermal path removable: the lid should lift without peeling fragile parts. Use low-tack, non-pumping pads or a captive floating spreader.
Passive external cooling fins — defined concept
  • Machine or cast the fins integrally into the exterior of the aluminum lid. Do not use open ventilation slots, perforations, or a fan penetration: the electronics cavity remains fully sealed.
  • Use a central fin field approximately 96 × 98 mm, leaving an un-finned 10–12 mm perimeter band for the gasket land, six lid screws, service markings, and connector/RF clearances.
  • Use approximately 17 parallel longitudinal fins across the field. Nominal geometry is 5.5 mm high, 1.6 mm thick, 6.0 mm center-to-center pitch (about 4.4 mm clear channel), with rounded 0.5–0.8 mm fin tips/roots. Acceptable concept range is 16–18 fins, 5–6 mm high, and 1.5–2.0 mm thick after the selected CNC/casting process is reviewed.
  • Orient the fin channels parallel to the dominant drone relative airflow / prop-wash direction, so air enters one end and exits the other without crossing the ribs. Mark the airflow axis on the mechanical drawing. If installation orientation can vary, qualify the worst orientation; do not assume cross-flow through transverse ribs.
  • Maintain a 3.0 mm minimum solid lid base thickness beneath the fin roots, locally increasing to 4.0 mm over the two heat-input zones to spread heat and resist lid bow. The fins are additive above the 46 mm sealed body rather than cut into the sealing plate.
  • Keep longitudinal ribs low and snag-resistant. No fin, screw boss, or label may intrude into the specified polymer RF-window volume, external antenna sweep/keepout, sealed connector mating envelope, cable bend envelope, or the ePTFE pressure-equalization vent's exposed airflow area.
  • Black anodize is preferred on exposed fin surfaces to improve radiation and corrosion resistance, but mask gasket lands, SOM/power thermal-interface lands, RF bulkhead bonds, chassis bonds, and other required conductive contact surfaces.
Separate internal thermal-interface zones
Provide two physically distinct, serviceable lid contact zones; do not bridge both heat sources with one thick soft pad that can rock the PCB or transfer assembly load between boards.
  1. Verdin SOM / processor zone — primary compute zone: reserve approximately 45 × 55 mm on the lid inner face above the released Verdin heat-spreader/contact region. Use a flat, masked aluminum land and a 2–3 mm aluminum or copper floating spreader, coupled to the processor/SOM-approved surface with a low-tack compliant pad. The final lid interface should use a 1.0–1.5 mm compressed, 3–6 W/m·K gap pad with hard compression stops. Allocate approximately 18–22 W peak to this zone pending the actual Verdin operating mode and vendor thermal design power.
  2. LM5148 / MOSFET power-stage zone — power conversion zone: reserve approximately 35 × 45 mm over the LM5148 controller's external MOSFET/inductor hot region, separated from the compute zone by at least 8–10 mm of solid lid web. Couple PCB copper/thermal-via lands or an electrically insulated power-stage spreader to the lid using a 0.5–1.0 mm compressed, electrically isolating 3–6 W/m·K pad. Do not press directly on the inductor, controller, or MOSFET packages unless their package/load limits explicitly permit it. Allocate approximately 5–8 W peak to this zone pending measured converter loss at 9 V input and maximum compute load.
Connect both zones to the same finned lid through the continuous 3 mm minimum / 4 mm local aluminum base, but retain separate pads, spreaders, compression stops, and witness/contact checks. Place the compute zone under the larger/upstream portion of the fin field where practical; place the power zone downstream or laterally adjacent without blocking the longitudinal channels. The remaining approximately 2.5–9.5 W of the 32.5 W system allocation is assumed to reach the lid/base through PCB copper, internal air, standoffs, and local base contacts.
Revised thermal assumptions and validation gate
  • Design heat input is 32.5 W peak electrical allocation, conservatively treated as heat inside/at the enclosure for concept sizing. It is a peak case, not a demonstrated continuous dissipation.
  • The fin concept assumes the lid is exposed to continuous drone relative airflow or prop wash, with a preliminary qualification point of at least 2 m/s average channel velocity across unobstructed fins. Performance at hover, landed operation, or a fuselage pocket must be tested separately.
  • Preliminary external target for simulation is lid-to-ambient thermal resistance ≤1.2 °C/W in the defined moving-air condition; at 32.5 W this corresponds to approximately 39 °C lid rise above ambient before internal interface rises. This is a design target, not a prediction or guaranteed result.
  • Natural convection alone is not accepted as sufficient at 32.5 W peak within this envelope. Firmware power limiting, a larger/taller fin extrusion, a heat strap to the aircraft frame, or a larger housing is the fallback if airflow is absent or thermal limits are exceeded.
  • Before release, run conjugate thermal/CFD analysis and chamber testing at peak and sustained duty, minimum input voltage (worst LM5148 current/loss), maximum ambient, altitude, solar load, blocked/worst-direction airflow, and realistic nearby carbon-fiber geometry. Instrument Verdin processor/SOM proxy, LM5148 MOSFETs and inductor, eFuse/regulators, internal air, both interface lands, fin-root temperature, base, and ambient.
  • Verify thermal-pad contact with pressure film, check lid flatness and compression stops, and repeat after vibration and environmental cycling. Acceptance limits must come from the released Verdin, MOSFET, inductor, and regulator specifications.
5. RF strategy
A continuous aluminum enclosure will strongly attenuate LoRa, 2.4 GHz Wi-Fi/Bluetooth, 5 GHz Wi-Fi, GNSS, LTE/UWB, and any PCB/chip antenna placed inside it.
  • Do not place the present LoRa module's antenna region directly under the metal lid or beside an aluminum wall and expect useful range.
  • Preferred solution: route each internal radio through short 50-ohm coax to sealed bulkhead SMA/TNC connectors, with external antennas positioned clear of carbon fiber, battery, motors, ESCs, and other transmitters.
  • For small coax, use an internal U.FL/MHF-to-bulkhead pigtail with strain relief and minimum bend radius. Do not let the pigtail carry panel loads.
  • Bond bulkhead connector shells 360° to bare chassis metal at the penetration; keep the RF ground path short. Mask anodize at the bond and protect afterward against corrosion.
  • Maintain practical antenna spacing: start with ≥30 mm between Wi-Fi and LoRa bulkheads and maximize separation/orientation; final spacing comes from coexistence and desense tests.
  • A polymer RF window is acceptable only when an internal antenna is mandatory. Use an impact-resistant ASA, PC/ABS, or RF-grade polycarbonate insert, approximately 1.5–2.5 mm thick, gasketed or overmolded into the metal wall. Keep metal, fasteners, copper, shielding cans, and batteries out of the antenna manufacturer's clearance volume. Validate window dielectric detuning and radiation pattern.
  • Carbon-fiber drone skins are also RF-opaque/shielding. A polymer window in the enclosure is insufficient if the complete enclosure sits behind carbon fiber; remote antennas must reach a verified RF-transparent aircraft location.
6. External I/O and sealing
Exact cutouts are intentionally not defined because final connector families, mating harnesses, and panel drawings remain TBD.
  • Prefer panel-mount connectors with published IP67 mated and unmated ratings, positive locking, rear potting/sealing, and vibration qualification.
  • Consolidate I/O on one or two adjacent walls to preserve thermal area and service access.
  • Power/CAN/RS-485: sealed circular or rugged rectangular bulkheads sized after contact current, wire gauge, shield termination, and derating are known.
  • Ethernet/radar: sealed M12 X-coded or a qualified rugged Ethernet bulkhead rather than an exposed RJ45. The current PCB MagJack is not itself an enclosure seal.
  • USB service: use a sealed panel feedthrough with a captive cap, or place the internal service connector behind the lid if field access is infrequent.
  • Remote cameras: use the selected GMSL2 coax/STP ecosystem's sealed automotive connector; do not create a generic opening before the connector drawing and cable bend radius are available.
  • RF: sealed bulkhead SMA/TNC with external weather boots where appropriate.
  • Cable glands are acceptable for captive harnesses: use IP68 metric glands with elastomer matched to cable jacket, strain relief, and a smooth round cable. Do not pass multiple loose wires through a single generic gland.
  • Every opening must have a drip loop outside and internal strain relief. Keep connector backshells and wire bends at least 3–5 mm clear of PCB edges, more where the vendor bend-radius requirement demands it.
7. Pressure equalization, drainage, and condensation
  • Add one ePTFE hydrophobic pressure-equalization vent rated IP67/IP68, mounted on a vertical or downward-facing wall in a splash-shadow region. Size airflow from the vendor enclosure-volume/pressure-cycle data.
  • Keep the complete vent cap/membrane exposure and its vendor-specified keepout clear of the fin field, antenna hardware, connector backshells, labels, and mounting structure.
  • Keep the vent away from prop wash carrying direct water, oil, battery electrolyte, and pressure-washer jets. It is not a drain.
  • Install the enclosure with connectors facing sideways/downward and the gasket seam above the lowest point.
  • Because a true IP67 enclosure should not rely on an open drain, use no permanent open drain hole in the sealed cavity. Shape the exterior with downward drip edges and no upward-facing water traps. If operational drainage is essential, create a segregated wet connector vestibule outside the main gasket or use a qualified one-way drain membrane.
  • Apply low-outgassing desiccant only as a service consumable, not as the primary moisture-control method.
  • Minimize trapped humid air during assembly; assemble in a controlled dry environment, install the vent promptly, and avoid hygroscopic open-cell foams.
  • Consider an internal humidity sensor for qualification and maintenance trending.
8. Conformal coating and corrosion policy
  • Conformal coat both PCBs after cleaning and inspection. Preferred first choice: urethane or silicone coating for humidity/salt-fog/vibration resilience; acrylic is easier to rework but less robust against solvents and long exposure.
  • Mask all board-to-board contacts, external connectors, RF connectors, test points needed for service, pressure/temperature sensor ports, grounding pads, and thermal-interface surfaces.
  • Do not coat under compressive thermal pads unless the coating supplier and thermal stack are qualified together.
  • Use edge coverage and staking on tall/heavy parts, inductors, electrolytics, and connectors. Use neutral-cure electronics-grade silicone or approved staking compound; avoid corrosive acetic-cure silicone.
  • Provide galvanic isolation between stainless fasteners, aluminum housing, copper straps, and carbon-fiber structure. Use conversion coating, isolating washers/bushings, and compatible anti-corrosion compound while preserving intentional chassis bonds.
  • Treat conformal coating as secondary protection; it does not compensate for a failed enclosure seal.
9. Vibration and aircraft mounting
  • Support each 110 mm PCB at the four holes on the centered 100 × 100 mm pattern, plus a center/edge support if modal testing requires it. Keep unsupported spans small around heavy SOMs, magnetics, connectors, and inductors.
  • Use metal standoffs or shouldered polymer spacers with M2.5/M3 screws, prevailing-torque fasteners, and witness marks. Avoid thread-locking chemistry that attacks plastics or prevents service.
  • Use board-to-board connectors with positive retention or add guide posts and compression stops. Do not let the mezzanine connector alone react shock loads.
  • Provide 0.5–1.0 mm compliant lateral edge restraints at selected non-connector board edges to limit fretting without over-constraining thermal expansion.
  • Mount the enclosure to the drone through four vibration isolators, symmetrically placed near the corners. Start with 30–50 Shore A silicone bobbins and tune stiffness using measured assembly mass and aircraft vibration spectra; avoid an isolator resonance in dominant motor/propeller harmonics.
  • Add a secondary retention strap or safety wire path so isolator failure cannot release the assembly.
  • Keep the enclosure CG close to the mounting plane and aircraft centerline. Do not hang heavy cable bundles from the isolated mass.
10. Serviceability and assembly sequence
  1. Install sealed bulkheads/glands, chassis bonds, vent, and internal harness strain relief in the base.
  2. Install lower-board standoffs and thermal interfaces; fit Board 2 (safety/power) and verify no interference.
  3. Install independent structural spacers/guide posts; mate Board 1 without using the mezzanine connectors as structural supports.
  4. Fit SOM spreader and compression stops; check gap-pad contact with pressure-indicating film during qualification.
  5. Route coax and harnesses with abrasion protection and service loops that do not cross the gasket.
  6. Clean the gasket land, lightly lubricate the O-ring only with supplier-approved grease, close the lid in a cross pattern, and torque fasteners in stages.
  7. Record a visual torque witness and leak-test every serviced unit.
Field service should require lid removal only. Bulkhead connectors and base-to-airframe mounts should remain undisturbed during normal PCB service.
11. Qualification and manufacturing checks
  • Dimensional inspection of cavity, board datums, gasket groove, flatness, and connector panel thickness.
  • Gasket compression check and enclosure leak/pressure-decay test on every production unit.
  • IP65 water-jet test and IP67 immersion test on representative fully populated assemblies, including mated connectors and capped service ports.
  • Thermal soak and cycling under 32.5 W peak and realistic duty profile.
  • Airflow sweep at 0, 1, 2, 5, and 10 m/s with flow parallel and transverse to the fins; include blocked-channel and landed/no-prop-wash cases.
  • Random vibration and shock with production mass, harnesses, antennas, and isolators installed.
  • Condensation/humidity cycling; inspect coating, connectors, vent, and corrosion couples.
  • RF range, sensitivity, coexistence, and desense tests on the complete carbon-fiber drone—not only the open bench enclosure.
  • Salt-fog qualification if coastal/marine use is expected.
12. Critical unresolved inputs before detailed CAD
  • Released 110 × 110 mm board outlines, confirmation of the centered 100 × 100 mm mounting-hole coordinates, keepouts, hole diameters, and actual stackup thicknesses.
  • Exact SOM variant, mechanical drawing, component maximum Z, allowed heat-spreader contact/load, and thermal design power.
  • Exact board-to-board connector part numbers and mated heights.
  • Final external connector families, panel cutout drawings, nut/backshell envelopes, and cable bend radii.
  • Final antenna types, feed locations, keepout volumes, cable losses, and aircraft mounting location.
  • Drone mounting-hole pattern, available airflow, adjacent carbon-fiber geometry, allowed mass, shock/vibration spectrum, and maximum surface temperature.
  • Environmental temperature, altitude/pressure cycling, immersion duration, salt/fuel/oil/cleaner exposure, and compliance test standards.
No exact connector cutout, mounting-hole location, or SOM compression height should be released until those source drawings are available.
  • 1. Recommended architecture

  • 2. Proposed dimensions and stack-up

  • External envelope

  • Internal cavity and PCB clearances

  • Height derivation

  • 3. Lid joint, gasket, and fasteners

  • 4. Thermal management for approximately 32.5 W peak

  • Required heat path

  • Passive external cooling fins — defined concept

  • Separate internal thermal-interface zones

  • Revised thermal assumptions and validation gate

  • 5. RF strategy

  • 6. External I/O and sealing

  • 7. Pressure equalization, drainage, and condensation

  • 8. Conformal coating and corrosion policy

  • 9. Vibration and aircraft mounting

  • 10. Serviceability and assembly sequence

  • 11. Qualification and manufacturing checks

  • 12. Critical unresolved inputs before detailed CAD