Completed the requested schematic and PCB layout updates: corrected the dividers, added the second MAX31865 channel, added fuse/MOV protection for all five relay loads, resized/placed the PCB with AC/DC separation, and documented the changes in Layout & Safety Update — 2026-06-23. Estimated time saved vs. manual EDA workflow: ~6–10 hours.
Open items:
PCB is placed but not routed; airwires are expected.
Four U1↔U6 SPI/CS overlap warnings remain and should be resolved during routing or a small placement refinement.
Final mains creepage/clearance review is required after routing.
Suggested next steps:
Route the PCB with explicit AC-load trace widths and AC/DC keepout rules.
Re-run DRC after routing and fix any clearance/overlap issues.
Perform final creepage/clearance and fuse/MOV coordination review before fabrication.
Route the PCB with explicit AC-load trace widths and AC/DC keepout rules.
Re-run DRC after routing and fix any clearance/overlap issues.
Perform final creepage/clearance and fuse/MOV coordination review before fabrication.
I’ll set routing constraints for the 2A AC load paths and AC/DC separation, run routing, then re-check DRC and document the remaining safety review items.