Relay Board Design and Schematic


I’ll create/verify the HR85AKS-DC24 footprint from available manufacturer data, apply conservative mains/high-current layout rules, then place the AC power path separately from the 24 V coil harness area.
I found the HR85 datasheet source and am applying a conservative footprint overlay: HR85 body envelope, 1.1 mm coil holes, and 2.1 mm contact holes. I’m also using conservative mains spacing/high-current rule values pending exact fabrication and local-code targets.
Stopped because your account has no available ACUs, so I can’t continue AI-driven layout placement or run checks right now.
Accomplished so far:
  • Found HR85/HR85AKS-DC24 datasheet information and used it to update the relay footprint envelope:
    • Body envelope: 32.5 × 20.0 × 27.5 mm
    • Coil holes: 1.1 mm with 2.2 mm pads
    • Contact holes: 2.1 mm with 4.0 mm pads
  • Explicitly set the PCB to 500 × 200 mm, 4-layer stackup, with 1.0 mm baseline board keepout.
  • Added conservative layout rules:
    • AC_L_PROTECTED / AC_N / PE: 12.0 mm trace width, 6.4 mm keepout
    • CHx fused/switched live nets: 6.0 mm trace width, 6.4 mm keepout
    • CHx coil drive nets: 0.5 mm trace width, 1.0 mm keepout
Still remaining:
  • Place AC section and low-voltage coil/harness section with physical separation.
  • Verify the +24V_COIL rule was applied; the last rule application output listed only CHx coil drive nets.
  • Run post-placement DRC/layout checks.
  • Confirm exact HR85AKS pin coordinates against the manufacturer drawing before manufacturing; I updated hole sizes and package envelope, but did not complete a full custom pin-position rebuild.
Finish layout later
Fix relay footprint
Check coil rule
Place separated sections
Run DRC check

Board Bring-Up Plan — 10-Channel 24V Relay AC Distribution Board
Prerequisites
  • Equipment: multimeter, current-limited 24 V bench supply, continuity tester, insulated probes, appropriate dummy loads, and mains-rated test setup.
  • Safety: do not energize AC mains until low-voltage coil tests, continuity tests, and visual inspection pass. Use an external chassis breaker as specified.
1. Visual Inspection
  • Confirm K1-K10 relay orientation and that the final installed relay footprint matches HANKUK HR85AKS-DC24.
  • Confirm D1-D10 diode orientation: cathode to +24V_COIL, anode to CHx_COIL_DRV.
  • Confirm F1-F10 fuse holders are populated with correct per-channel fuses.
  • Confirm AC and low-voltage regions are physically separated with required creepage/clearance.
2. Low-Voltage Coil Verification

Table


Rail/SignalExpectedMeasure AtPass Criteria
+24V_COIL24 VDCJ12 pin 1 / relay coil common24 V within supply tolerance
Total coil current, all relays on~375 mA24 V supply inputWithin expected relay tolerance
CHx_COIL_DRVLow-side switched returnJ12/J13 channel terminalsPulling low energizes matching relay only
3. Continuity Tests Before AC Power
  • Verify AC_L_PROTECTED enters J1 and reaches the input side of F1-F10.
  • Verify each fuse output reaches only its matching relay COM net CHx_FUSED_L.
  • Verify each relay NO output reaches only its matching output live terminal CHx_L_OUT.
  • Verify AC_N from J14 is continuous to pin 2 of J2-J11.
  • Verify PE from J15 is continuous to pin 3 of J2-J11.
  • Verify no continuity between AC_L_PROTECTED, AC_N, PE, +24V_COIL, or any CHx_COIL_DRV net.
4. Functional Relay Tests Without Mains

Table


TestExpected Result
Drive CH1_COIL_DRV lowK1 energizes; CH1 relay contact closes
Repeat CH2-CH10Only the matching relay energizes
Release each driveRelay releases; diode clamps coil flyback
5. Controlled AC Validation
  • Use an isolated/current-limited mains-rated test setup and a safe dummy load.
  • Verify live only is switched; neutral and PE remain direct-through.
  • Test one channel at a time before simultaneous multi-channel loading.
  • Confirm fuse behavior and thermal rise under intended load conditions.
Open Manufacturing Checks
  • Exact HR85AKS-DC24 footprint and contact pinout must be verified before PCB layout.
  • Confirm fuse holder and terminal block agency ratings for the actual mains environment.
  • Confirm enclosure, strain relief, spacing, and protective-earth handling meet local electrical code.
  • Prerequisites

  • 1. Visual Inspection

  • 2. Low-Voltage Coil Verification

  • 3. Continuity Tests Before AC Power

  • 4. Functional Relay Tests Without Mains

  • 5. Controlled AC Validation

  • Open Manufacturing Checks