USB4 PCIe Bringup


Yes—combining several smaller raw NAND chips behind one SSD controller is how many SSDs are built. For example, four 512 GB NAND packages could provide roughly 2 TB of raw capacity, with some reserved for reliability and management.
The architecture would be Mac → ASMedia USB4 bridge → one NVMe SSD controller → multiple NAND chips. The Mac would see one drive, so this approach does not inherently prevent Apple silicon Mac compatibility.
The difficulty is getting an SSD controller with firmware that explicitly supports the exact NAND parts, plus usable design documentation. NAND chips are not interchangeable. This is possible, but considerably harder than using one complete solder-down SSD—and combining multiple complete SSD chips is a different architecture that needs additional switching or bridging.
That’s fine. Maybe if the user wants more than the largest single solder down SSD, we use a new architecture to support it
Agreed. We’ll favor one complete solder-down NVMe SSD for the simpler design, and treat capacities beyond the largest qualified single device as a separate, multi-SSD architecture with its own power, firmware, and Mac compatibility validation. No board changes yet.
But the machine must see it as one drive is the only requirement
Understood—the Mac must see one drive, not multiple drives combined through macOS software. A single solder-down SSD already meets that requirement; a larger, multi-SSD version would need hardware aggregation that exposes one logical storage device over USB4.
A PCIe switch alone does not combine SSDs into one drive. That larger version would need a suitable hardware RAID/storage controller and verified Mac-compatible firmware. Also, combining drives for capacity does not automatically provide redundancy—failure of one SSD could lose the entire volume.
Understood. I like this direction but I’m not ready to build yet
Understood—we’ll keep this as a concept and leave the board unchanged. The preferred direction is a single solder-down NVMe SSD, with a separate higher-capacity architecture only if needed; either way, the Mac must see one drive.

Board Bring-Up Plan
2026-09-28 authoritative bring-up update
This section overrides stale counts and historical USB-C statements later in the file.
Hardware state
  • U10 TPS65987D is the only CC/PD owner; U1 CC pins must remain disconnected.
  • The configuration flash/strap hardware supports VBUS-powered dead-battery boot. Do not connect an SSD or enable full rails until U11 contains a read-back-verified image limited to 5 V fallback and 9 V/3 A.
  • U3 uses R34 = 470 kΩ / R35 = 200 kΩ. Expected source thresholds are 3.91-4.16 V rising and 3.56-3.79 V falling. Canonical EN/UVLO connectivity is correct. R4 now senses input-side VBUS_RAW for the OVLO divider, and C10 is rated 25 V.
  • U7 TPS22965DSGR is suitable for the 4 A SSD transient planning point by current rating (6 A continuous, 8 A short pulse). C14 = 10 nF/25 V sets about an 11.8 ms ramp, and C34 = 1 µF/10 V is now placed and locally connected at VIN.
  • U7 now has R40 = 100 kΩ default-OFF pull-down and C37 = 100 µF local input-side bulk; retain controlled startup and verify surge/thermal behavior on the bench.
  • U4/U5/U6 support is no longer placeholder-only: bootstrap, feedback/VSET, rated inductors, and output/input capacitors are present. R1 is a 10 mΩ, 3 W 2512 shunt. Regulator compensation, effective capacitance, transient response, and thermal validation remain mandatory.
  • Production blocker: the live U10 library part maps the SPI PICO/POCI names to physical pads 36/37 opposite TI's physical pin definitions. Do not approve the U10/U11 SPI interface until a corrected source part is placed and the flash nets are reverified.
  • Keep D12 SMAJ12A only with the strict 9 V image. Any future 15 V/20 V PDO requires a new TVS coordination review.
  • Keep J4. It is explicitly rated by the manufacturer for USB4 Gen3 / 40 Gbps and 5 A.
  • Do not move or rotate J2. Clear R17, C2, and R1 from the M.2 module keepout instead.
Current layout/review status
  • Board: 100 x 80 mm, eight copper layers.
  • Active U10: approximately (34 mm, 28 mm). Duplicate PCB-only U10 at approximately (38.8 mm, 0 mm) is inactive.
  • R17, C2, and R1 are outside the M.2 module keepout; J2 orientation remains unchanged. Added/replaced power parts are on-board.
  • Focused switching-power-stage review has no open findings. Placement still has four pre-existing component overlaps around U11/U9 and six unrelated parts outside the board.
  • Current DRC reports 88 overlapping-copper errors, dominated by stale/shorting existing routing after placement and component changes. Broad autorouting is prohibited until those shorts and stale routes are cleared deliberately.
Mandatory staged power test
  1. Unpowered: verify no hard short on VBUS_PORT, VBUS_RAW, VBUS_PROT_9V, 3V3_LOGIC, 1V9, 1V05, BUCK_3V3_PRE_SWITCH, or SSD_3V3. Verify U7 is off and the SSD rail is isolated.
  2. 5 V fallback, no SSD: use a protected PD analyzer or current-limited fixture. Confirm U10 boots from VBUS/U11, VBUS remains near 5 V, and U4/main rails remain disabled. Stop if any 15 V/20 V request appears.
  3. 9 V contract, no SSD: negotiate exactly 9 V/3 A. Confirm VBUS_PORT, VBUS_RAW, U3 output, and then 3V3_LOGIC in sequence. Confirm U5/U6 EN rise only after 3V3_LOGIC.
  4. Confirm ASM_VBUS_SENSE_3V3 stays within 0-3.3 V and never follows 9 V amplitude.
  5. Verify 3.3 V, 1.9 V, 1.05 V, reset, clock, and both SPI interfaces before enabling U7.
  6. SSD test: fit a known low-power NVMe SSD first. Capture U7 VIN/VOUT, input current, ramp time, and case/board temperature. Pass only if the approximately 11.8 ms ramp is monotonic, the rail remains in tolerance, and no eFuse/load-switch limiting occurs.
  7. Increase SSD load only after thermal and transient data demonstrate margin. A guaranteed worst-case U7 RON value is not available for VIN = VBIAS = 3.3 V, so bench validation is a release requirement.
No-go conditions
  • Missing, unreadable, or unrestricted TPS65987D image.
  • Any 15 V/20 V contract request with D12 installed.
  • U3 EN/UVLO tied directly to VBUS_RAW or OVLO not sensing the input rail.
  • U10/U11 SPI verified using the defective pad-36/pad-37 library mapping.
  • U5/U6 rails out of sequence, unstable, or outside tolerance despite the completed first-pass support networks.
  • M.2 keepout violations, out-of-board parts, routing pre-check blockers, airwires, redundant copper, or blocking DRC.
  • Missing ASMedia GPIO2/UART_TX policy, production firmware, or verified 25 MHz clock implementation.
Status and release verdict — 2026-08-27 live review
Current-state notice: The USB-C/PD and J4 statements in the dated update under “First-power procedure” supersede older pre-change text retained elsewhere in this file. The schematic target block passes focused ERC; only U1 GPIO2, U1 UART_TX, and U5_BOOT_PLACEHOLDER remain in the focused electrical checks.
Schematic: 61 components, 78 nets. PCB: 62 elements/footprints, 8 copper layers, 1.47 mm nominal stackup. The extra PCB-only element U10 has no matching live schematic component and must be reconciled.
Current checks: 143 airwires, 21 dangling-trace groups, 163 overlapping-copper errors, 46 floating-pin ERC errors, and 1 single-pin-net ERC error (U5_BOOT_PLACEHOLDER). No missing-footprint finding was returned, and every schematic component has a PCB footprint, but the PCB has the unmatched U10 element. SI and power-integrity review engines returned no matching review results, so they are unavailable/unrun, not passes.
Autorouting verdict: NO-GO. Do not autoroute until the schematic blockers below are resolved, J4 is fully connected, stale/dangling/shorting copper is removed, BGA escape geometry is approved, and fab impedance rules are loaded.
Fabrication verdict: NO-GO. The current board is electrically incomplete and has open routing, copper shorts, unresolved power sequencing, connector omissions, unverified impedance/plane behavior, and missing firmware/configuration.
Live design facts
M.2 / PCIe
J2 is connected to U1 for PCIe Gen4 x4: all four PCIE_TX[0..3]_TO_M2 pairs, all four PCIE_RX[0..3]_FROM_M2 pairs, PCIE_REFCLK*_TO_M2, M2_PERST_N, M2_CLKREQ_N, M2_PEWAKE_N, M2_PEDET_PCIE, SSD_3V3, and GND are present. Direction and connector pin mapping are documented in M.2 NVMe Connector Mapping.
Live blockers: U1 GPIO2 (x4 PRSNT#/INS# policy) and UART_TX (MEMREPAIR policy) are floating. Their final strap/connection policy requires authoritative ASMedia guidance; do not guess.
ASM2464PDX support
Present in the live schematic:
  • Rails: 3V3_LOGIC to VCCH/VCCA33, 1V9 to VCCL, 1V05 to VDD, and GND.
  • ASM_REXT_12K1_REQUIRED is connected through R13 = 12.1 kΩ to GND.
  • 25 MHz network: XI_25M, XO_25M, R14 = 2 MΩ, C7/C8 = 15 pF.
  • Reset: U9 drives ASM2464PD_RST_N_UNEXPOSED.
  • SPI: U8 connects to U1 CS#, CLK, DI, and DO; CS#/WP#/HOLD# support pull-ups are present.
  • SSD power enable: U1 HDDPC drives U7 ON.
Blockers:
  • No crystal/resonator component or exact crystal MPN is present between XI/XO; insertion and load-capacitance validation remain TODO.
  • Full per-ball BGA decoupling mapping is not demonstrated. The large VCCH/VCCL/VDD ball groups are aggregated onto rails with only limited visible rail capacitors; obtain the vendor decoupling map and implement/verify each required domain.
  • ASMedia production SPI firmware/configuration image and programming procedure are unavailable.
  • GPIO2/PRSNT# and UART_TX/MEMREPAIR policies are unresolved.
USB-C and power
Live implementation update: J4 VBUS_PORT feeds U10 TPS65987DDKRSHR, then VBUS_RAW feeds U3 and VBUS_PROT_9V. U10 is the sole CC/PD owner; U1 CC pins are NC and U1 receives protected ASM_VBUS_SENSE_3V3. R33 sources 3V3_LOGIC, and U5/U6 EN follow 3V3_LOGIC. The older fixed-5 V paragraphs below are historical.
Live path: J4 VBUS contacts → VBUS_RAW → U3 TPS259474 eFuse → VBUS_PROT_9V. J4 CC1/CC2 connect to U1 through D10. U1 is directly tied to raw VBUS sensing.
Power rails:
  • BUCK_3V3_PRE_SWITCH from U4, then U7 switches to SSD_3V3.
  • 3V3_LOGIC supplies U1 VCCH/VCCA33, U8, U9, and U7 bias, but has no verified source.
  • U5 targets 1V05; U6 targets 1V9.
Known power blockers, confirmed against the live nets and Power Budget Analysis:
  • U5 BOOT is a single-pin placeholder; feedback/output implementation is not validated.
  • U6 VSET/S-CONF uses placeholder nets and is not validated for 1.9 V.
  • U5 and U6 EN are tied to protected VBUS, while the required VCCH-first sequence is not implemented.
  • U4 EN divider prevents intended operation from a 5 V input; 3V3_LOGIC remains unsourced.
  • No verified enforcement of USB-C Default/900 mA/1.5 A/3 A advertisement exists. U3 is capped near 3 A, but it does not dynamically track CC advertisement.
  • Higher-voltage PD is blocked because U1 VBUS is 5 V-tolerant and directly connected to VBUS_RAW; vendor-approved sensing/isolation and sequence architecture are required.
  • U7 is rated 3.8 A continuous, below the current 4.0 A SSD transient planning allowance. Decide whether to restrict supported SSDs or replace the switch after the source architecture is fixed.
High-speed metadata
J4 continuity update: all J4 USB4, USB2, SBU, CC, VBUS, GND, and mounting/shield terminals are now connected. Physical SI validation remains pending routing and a fab-confirmed stackup.
Fourteen differential pairs are detected from live net properties: 8 PCIe data pairs at 85 Ω, 1 PCIe REFCLK pair at 100 Ω, 4 USB4 pairs at 85 Ω, and 1 USB2 pair at 90 Ω. Each has a matching pair name, bus group, partner, and 0.1 mm P/N skew property.
This metadata does not make the channel complete: J4 USB4 TX/RX, USB2 D+/D−, and SBU pins remain floating. The current high-speed nets terminate at protection devices/U1 rather than continuing to J4. No SI review result is available, and stackup/trace/via geometry is not fab-confirmed.
Bring-up prerequisites — all must pass before applying power
  1. Resolve U1 GPIO2/PRSNT# and UART_TX/MEMREPAIR policy from ASMedia documentation.
  2. Install and validate the exact 25 MHz crystal MPN and load network.
  3. Complete vendor-required BGA decoupling and power sequencing.
  4. Complete U5/U6 circuits and validate all programmed output values.
  5. Resolve USB-C PD/current-advertisement enforcement and U1 VBUS sensing.
  6. Resolve the 3.8 A SSD switch decision.
  7. Connect J4 high-speed/USB2/SBU paths with approved protection devices and channel topology.
  8. Obtain the ASMedia SPI firmware/configuration image and programming method.
  9. Remove all 163 copper overlaps, 21 dangling-trace groups, and 143 airwires; reconcile PCB-only U10.
  10. Obtain fab-approved 8-layer stackup, 85 Ω/90 Ω/100 Ω geometries, via/antipad rules, BGA escape capability, and plane requirements. Re-run DRC/SI after loading them.
First-power procedure
USB-PD contract and safe first-power update — 2026-08-27
  • PCB outline was enlarged from 100 x 45 mm to 100 x 80 mm. The new PD/VBUS parts were placed in the added upper area with no component-body overlaps; J1/J2 orientations were not changed and no routing was performed.
  • Layout inspection still reports a second legacy 2 x 2 mm PCB-only element named U10 at (38.8 mm, 0 mm). The layout-node delete API could not remove element nodes, so this orphan must be deleted manually or by a future element-delete tool before fabrication.
  • U10 TPS65987DDKRSHR is the sole CC/PD owner. U1 ASM2464PDX CC1/CC2 are intentionally disconnected.
  • Program U11 W25X05CL with the TI-generated, ASMedia-compatible bundle before functional USB4 testing. The bundle must advertise/request a fixed 9 V / 3 A sink contract and must not request 15 V or 20 V.
  • Safe fallback is 5 V only; the LM5143 UVLO keeps the main rails disabled at 5 V. If VBUS_RAW does not settle near 9 V, do not bypass UVLO or raise current limits.
  • U3 remains limited to approximately 3.00 A and its OVLO rising threshold is approximately 10.27-10.62 V.
  • Expected ASM_VBUS_SENSE_3V3: approximately 0 V before 3V3_LOGIC is valid or when protected VBUS is absent; approximately 3.3 V when 3V3_LOGIC and protected VBUS are present. U1 must never be probed at 9 V on this pin.
Updated staged power test:
  1. With no SSD fitted, apply 5.0 V at J4 through a current-limited fixture. Confirm U10 boots from VBUS, VBUS_RAW remains at 5 V, and U4/3V3_LOGIC remain off because the 9 V contract is absent.
  2. Program/verify U11, then connect a PD analyzer/source limited to 9 V / 3 A. Confirm the contract reaches 9 V before U4 starts.
  3. Confirm VBUS_PORT ≈ 9 V, VBUS_RAW ≈ 9 V minus U10 switch drop, VBUS_PROT_9V follows through U3, then 3V3_LOGIC rises first. Verify U5/U6 EN rise only after 3V3_LOGIC.
  4. Confirm ASM_VBUS_SENSE_3V3 is 3.3 V maximum and never follows raw VBUS amplitude.
  5. Start at 100 mA current limit for assembly fault screening; increase only in controlled steps after each rail passes. Do not install the SSD until all controller rails and reset behavior pass.
J4 tests:
  • Power-off continuity: all four VBUS contacts -> VBUS_PORT; CC1/CC2 -> U10 only through D10; USB2, SBU, and all eight USB4 pins -> their named controller/protection nets; signal grounds and MH1-MH4 -> GND.
  • Verify D12 polarity: cathode to VBUS_PORT, anode to GND.
  • Test both cable orientations with a PD analyzer. Pass only if the 9 V / 3 A contract is stable, U10 reports the attach over I2C2/IRQ, U1 VBUS sense remains 0-3.3 V, and no 15/20 V request occurs.
Remaining vendor/configuration blockers: the exact TI TPS65987D bundle and ASMedia host-interface behavior are not available in the public project sources; USB4/TBT discovery and entry must be validated with the production configuration image. The supplied hardware-photo URLs could not be decoded by the available inspection service, so no photo-only marking claim was used.
Do not install the NVMe SSD. Do not connect a host USB-C port. Use a bench supply at J4 VBUS/GND or a protected fixture.
  1. Unpowered checks:
    • Confirm no short from VBUS_RAW, VBUS_PROT_9V, 3V3_LOGIC, 1V9, 1V05, BUCK_3V3_PRE_SWITCH, or SSD_3V3 to GND.
    • Confirm SSD_3V3 is isolated from BUCK_3V3_PRE_SWITCH while U7 is off.
    • Inspect BGA orientation, solder bridges, eFuse polarity, MOSFET orientation, and regulator switch nodes.
    • PASS: no hard short and resistance is stable/rising as capacitors charge. FAIL: fixed low resistance or unexpected rail-to-rail continuity; stop.
  2. Initial current-limited input:
    • Apply 5.0 V with a 100 mA current limit. Do not raise the limit if it immediately enters current limit or any device heats.
    • Verify VBUS_RAW ≈ input and VBUS_PROT_9V rises through U3 without overshoot. Despite its name, this net must remain a 5 V-class rail until the PD/VBUS-sense blocker is solved.
    • PASS: no thermal event, no current-limit latch, and protected VBUS is stable. FAIL: current limit, oscillation, eFuse fault, or heating; stop.
  3. Rail verification after sequencing fixes are implemented:
    • Verify 3V3_LOGIC first, then 1V9 and 1V05, against final regulator tolerances from the approved designs.
    • Check ramp monotonicity, startup order, ripple, and load-step response with an oscilloscope.
    • Keep SSD_3V3 off until controller rails and reset are valid.
    • PASS: every rail is in its approved tolerance, sequence, ripple, and thermal limits. FAIL: any out-of-order, missing, overshooting, or unstable rail.
Clock, reset, and SPI gates
  1. Clock: probe XI_25M/XO_25M with a low-capacitance active probe after the exact crystal circuit is installed.
    • PASS: stable 25 MHz oscillation and startup consistent with the crystal/ASMedia specifications.
    • FAIL: no oscillation, intermittent startup, wrong frequency, or excessive loading.
  2. Reset: monitor ASM2464PD_RST_N_UNEXPOSED and U9 output relative to 3V3_LOGIC, 1V9, and 1V05.
    • PASS: reset remains asserted until required rails are valid and releases once without chatter.
    • FAIL: early release, repeated reset, or wrong logic level.
  3. SPI continuity: verify U1↔U8 CS#, CLK, DI, DO and pull-ups on CS#/WP#/HOLD#.
  4. SPI activity/programming:
    • BLOCKED/TODO: ASMedia image, configuration, expected JEDEC/boot transactions, and programming method are unavailable. Do not invent contents.
M.2 continuity and functional gates
With power off, verify continuity end-to-end and absence of P↔N, lane-to-lane, and lane-to-GND shorts for:
  • PCIE_TXP/N0..3_TO_M2
  • PCIE_RXP/N0..3_FROM_M2
  • PCIE_REFCLKP/N_TO_M2
  • M2_PERST_N, M2_CLKREQ_N, M2_PEWAKE_N, M2_PEDET_PCIE
  • all J2 SSD_3V3 and GND contacts
PASS: each intended endpoint is continuous, adjacent pairs are isolated, and connector pin numbers match the documented M.2 mapping. FAIL: any swapped polarity/lane, open circuit, short, or connector pin conflict.
Only after all power and firmware gates pass, fit a known low-power NVMe SSD and enable U7 under current monitoring. PASS: SSD_3V3 ramps without U3/U7 current limiting, PERST#/REFCLK behavior is valid, and the link enumerates at the intended width/rate. FAIL: overcurrent, reset/clock failure, link training failure, or unexpected fallback; stop and capture logs.
USB-C continuity and functional gates
Current state: J4 is schematically complete. Verify VBUS to VBUS_PORT, CC1/CC2 to U10 (not U1), protected USB2/SBU/USB4 continuity, and MH1-MH4 to GND. The older expected-failure text below is superseded.
Power off:
  • Verify J4 VBUS contacts to VBUS_RAW, all J4 grounds to GND, and CC1/CC2 to U1 through D10.
  • Verify no short among CC, SBU, USB2, USB4 pairs, VBUS, and GND.
  • Expected current-state failure: J4 USB4 TX/RX, USB2 D+/D−, and SBU pins are not connected to the corresponding protected/controller nets.
After J4 completion and approved power policy:
  • Test orientation in both plug flips.
  • Confirm detected source-current advertisement is enforced before enabling high load.
  • Confirm U1 VBUS sense never exceeds its approved rating.
  • PASS: both orientations enumerate, no CC/PD fault occurs, current remains within the active contract/advertisement, and USB4 link training is stable. FAIL: only one orientation works, overcurrent occurs, VBUS sensing is overstressed, or link training is unstable.
Final release gates
Autorouting GO only when
  • Schematic ERC has no unexplained errors; vendor-policy exceptions are explicitly documented.
  • J4 and power circuits are complete.
  • Stackup, impedance, via, BGA escape, and plane constraints are fab-confirmed.
  • Stale/shorting copper is cleared before a new route attempt.
Fabrication GO only when
  • Zero airwires, dangling traces, copper shorts, missing/orphan footprints, and critical ERC/DRC errors.
  • SI checks pass for every USB4, USB2, PCIe, and REFCLK pair, including protection footprints, vias, return planes, and connector launches.
  • Power-integrity/thermal checks pass for VBUS and all rails.
  • Required ASMedia firmware/configuration and production programming flow are available.
  • A completed bring-up unit passes every power, clock, reset, SPI, M.2, USB-C, and thermal gate above.
  • 2026-09-28 authoritative bring-up update

  • Hardware state

  • Current layout/review status

  • Mandatory staged power test

  • No-go conditions

  • Status and release verdict — 2026-08-27 live review

  • Live design facts

  • M.2 / PCIe

  • ASM2464PDX support

  • USB-C and power

  • High-speed metadata

  • Bring-up prerequisites — all must pass before applying power

  • First-power procedure

  • USB-PD contract and safe first-power update — 2026-08-27

  • Clock, reset, and SPI gates

  • M.2 continuity and functional gates

  • USB-C continuity and functional gates

  • Final release gates

  • Autorouting GO only when

  • Fabrication GO only when