Variable Frequency Drive PCB


Can you help me write a weekly report for this project with an abstract, images of the project, all the important things of the project, and a conclusion

flux

I’ll draft a weekly report with an abstract, project figures, progress, remaining issues and a conclusion. I’ll clearly separate the final 1 hp goal from the current low-voltage prototype and avoid claiming hardware tests that have not happened.
"VFD Capstone Progress Report" completed.

flux

I created your seven-page weekly report with two actual PCB images. The full schematic image was too zoomed out to read, so I used a board overview and an enlarged MCU-routing view instead.
Download your report
The report includes:
  • Abstract and project objectives
  • Specifications and system architecture
  • Captioned project images
  • PCB routing progress and branch-current analysis
  • Firmware results and component-rating concerns
  • Remaining challenges, next steps and conclusion
  • References to supporting project records
I saved a reading version in your project files: Weekly Progress Report.
Before submitting, fill in your name, course, instructor and reporting dates. The report distinguishes recent progress from cumulative work and clearly states that hardware testing and the final 230 V, 1 hp capability have not yet been demonstrated. Word pagination may vary; the PDF is the checked edition.

Weekly Project Report and Completion Plan
Project: 1 HP Three-Phase Variable-Frequency Drive
Student: Harvey Tada
Institution: South College
Reporting date: September 30, 2026
Team structure: Individual project
Current status: Advanced 48-60 V prototype design in progress; schematic ERC is clean, but PCB routing and fabrication verification are incomplete. The design is not yet safe to energize.

1. Landing Page: Abstract, Explanation, and Motivation
Abstract
This project develops a custom three-phase variable-frequency drive (VFD) for a 230 V, 1 hp induction motor. The VFD uses an STM32G474 microcontroller to generate 20 kHz complementary pulse-width-modulated signals and implement open-loop volts-per-hertz control from 0 to 60 Hz. The hardware includes a six-MOSFET three-phase inverter, three half-bridge gate drivers, phase-current measurement, independent hardware overcurrent shutdown, emergency-stop logic, DC-link precharge, auxiliary power supplies, temperature monitoring, programming interfaces, and an isolated USB connection for commands and telemetry.
The first hardware revision is intentionally limited to a 48 V nominal and 60 V maximum DC bus. This staged approach allows the control system, gate drive, sensing, precharge, protection, and firmware to be tested at lower energy before a future high-voltage design is considered. The prototype targets 5 A RMS phase current, 10 A short-duration peak current, nominal hardware trips at -12.004 A and +12.004 A, and coast-to-stop operation.
At the time of this report, the schematic contains 215 components and 105 nets. Schematic ERC is clean. Major power-stage, gate-driver, current-sense, protection, and precharge sections have been implemented, but the PCB remains incomplete with 206 airwires, 194 redundant copper objects in 63 groups, and 19 via-in-pad findings. Therefore, the project has not been released for fabrication or energized testing.
Project Motivation
Variable-frequency drives are important in industrial automation because they provide controlled motor speed, reduced mechanical stress during startup, process control, and potential energy savings. This project was selected to combine power electronics, embedded control, PCB design, sensing, protection, and software into one capstone system.
The main educational motivations are:
  • Understand how a DC bus is converted into variable-frequency three-phase output.
  • Develop practical experience with complementary PWM, dead time, and hardware timer shutdown.
  • Learn safe gate-driver, current-shunt, and high-current PCB layout practices.
  • Design protection that does not depend only on firmware.
  • Demonstrate disciplined staged validation instead of immediately operating from hazardous rectified mains voltage.
  • Produce a documented engineering process that includes requirements, design tradeoffs, failures, corrections, and verification.

2. Design Proposal and Design Ideas Considered
2.1 Selected Design
The selected design is a custom low-voltage three-phase inverter controlled by an STM32G474RET6. Six 150 V MOSFETs form three half-bridges. Three UCC27211A-Q1 drivers operate the high-side and low-side MOSFETs. Three 5 milliohm shunts and INA240A1 amplifiers measure phase current. Hardware comparators monitor positive and negative current limits, and logic gates combine the protection signals into a firmware-independent shutdown chain.
The DC-link precharge system uses four 100 ohm power resistors as the initial charging path and Q7 as the normal bypass path. A high-side LTC7001 driver controls Q7. Fused-side and bus-side divider networks generate PRECHARGE_VALID when the DC link reaches approximately 91 percent of the input voltage.
2.2 Design Alternatives Considered

Table


Design decisionAlternatives consideredSelected approach and reason
Development voltageBegin near 325 VDC or validate at low voltage48-60 V prototype selected to reduce shock, arc, and stored-energy risk during first validation.
Control methodScalar V/Hz, field-oriented control, direct torque controlOpen-loop V/Hz selected because it demonstrates true VFD operation with lower firmware and commissioning complexity.
Power stageIntegrated inverter module or discrete MOSFET bridgeDiscrete MOSFET bridge selected to expose gate-drive, protection, current-path, and PCB-layout design decisions.
Current measurementSingle DC-link shunt or three phase shuntsThree phase shunts selected for phase-specific measurement and protection.
ShutdownFirmware-only shutdown or independent hardware shutdownIndependent comparator, latch, logic, E-stop, gate-inhibit, and timer-break chain selected for safer fault response.
BrakingDynamic braking resistor or coast-to-stopCoast-to-stop selected for the first prototype to reduce hardware and control scope.
PC interfaceDirect non-isolated USB or isolated USB-UARTIsolated USB-UART selected to protect the laptop-side ground from the inverter ground domain.
PCBTwo-layer board or four-layer boardFour-layer board selected to improve routing resources, return paths, and power distribution.
2.3 Important Design Changes During Development
  • The target was reduced from an earlier higher-power concept to a 1 hp motor.
  • The first prototype was fixed at 48 V nominal and 60 V maximum.
  • The original overcurrent network was audited and found to trip at approximately -8.63 A and +33.38 A instead of the labeled +/-12 A. It was corrected to -12.004 A and +12.004 A.
  • A 2 uF load was removed from STM32 PA4, and a filtered 1.65 V reference was implemented.
  • The original TVS had only 58.10 V standoff, below the 60 V maximum bus. D1 was changed to a 1.5SMC75A-class device, and C1/C2 were upgraded to 100 V bulk capacitors for improved voltage coordination.
  • A TLV803EA30 supervisor was added so the inverter deterministically powers up in a faulted/inhibited state.
  • Q1-Q7, U8, and TP1-TP20 footprint copper required terminal-bound pad corrections to preserve valid lands and disable duplicate unbound copper.

3. Group Member Biography and Responsibilities
This is an individual project.
Harvey Tada
Harvey Tada is a South College student completing a capstone project in motor control and power electronics. His project responsibilities include requirements definition, architecture selection, component selection, schematic development, PCB placement and routing, protection analysis, BOM development, firmware planning, documentation, and preparation of the test procedure.
Primary technical areas developed during the project include:
  • STM32 motor-control architecture
  • Three-phase MOSFET inverter design
  • Gate-driver support circuitry
  • Current-shunt sensing and Kelvin routing
  • Hardware overcurrent and emergency shutdown
  • DC-link precharge
  • Isolated communication
  • PCB design-rule and manufacturing preparation

4. Time and Effort Table
Important: Exact hours were not recorded in the project files. Replace each Not recorded entry with the actual time from personal notes, calendar history, or laboratory records before submission. The dates and activities below are supported by the design history.

Table


Date or periodStudentActivity and contributionTime spent
Aug. 14, 2026Harvey TadaDefined project requirements, low-voltage prototype scope, motor target, and system architecture.Not recorded
Aug. 14-16, 2026Harvey TadaDeveloped schematic functional groups, selected primary devices, calculated preliminary power budget, and reconciled nets.Not recorded
Aug. 15-18, 2026Harvey TadaDeveloped overcurrent, E-stop, shutdown, and precharge circuits; performed datasheet verification.Not recorded
Sept. 5-9, 2026Harvey TadaReorganized the PCB power stage, corrected footprint-pad mappings, cleared stale traces, and routed initial high-current paths.Not recorded
Sept. 9, 2026Harvey TadaConsolidated the procurement BOM and identified sourcing blockers.Not recorded
Sept. 10, 2026Harvey TadaPerformed PCB routing-readiness review and established remaining routing priorities.Not recorded
Sept. 20, 2026Harvey TadaRedesigned and verified U2, U3, and U4 gate-driver cells and their local return paths.Not recorded
Sept. 20-21, 2026Harvey TadaRouted and reviewed U-, V-, and W-phase current-sense cells; corrected Kelvin and bypass geometry.Not recorded
Sept. 21-23, 2026Harvey TadaRouted protection logic, comparator thresholds, E-stop, fault latch, timer break, and gate-enable networks.Not recorded
Sept. 29-30, 2026Harvey TadaRecovered safety-cell routing, corrected TVS/capacitor ratings, added deterministic startup inhibit, and completed additional precharge routing.Not recorded
OngoingHarvey TadaMaintained reports, block diagrams, verification records, and final class documentation.Not recorded

5. Project Progress Log
Phase 1: Requirements and Architecture
The project began by defining a 1 hp, 230 V three-phase induction motor as the long-term load. Direct development at the approximately 325 VDC bus required for full-voltage operation was rejected for the first prototype. A 48-60 V low-voltage stage was selected to validate the inverter safely.
The architecture was divided into DC input protection, precharge, three-phase switching, gate drive, current sensing, hardware shutdown, auxiliary power, MCU control, temperature sensing, programming, local controls, and isolated USB communication.
Phase 2: Schematic Development
The schematic was expanded into a complete control and power architecture. Major accomplishments included:
  • STM32G474 controller and SWD interface
  • Three UCC27211A-Q1 gate drivers
  • Seven BSC074N15NS5 MOSFETs
  • Three INA240A1 current-sense channels
  • Six comparator thresholds for bidirectional overcurrent detection
  • Emergency-stop input and asynchronous fault latch
  • Qualified reset and final gate-enable logic
  • DC-link precharge and Q7 bypass system
  • 12 V, 5 V, and 3.3 V auxiliary rails
  • CP2102N, ISO7721, USB-C, and ESD protection
Schematic ERC is currently clean.
Phase 3: Protection Corrections
Several serious issues were found through review rather than assumed correct from labels:
  1. The original current limits were incorrect. The threshold network was recalculated and corrected to -12.004 A and +12.004 A.
  2. The MCU reference node had excessive capacitance. PA4 was separated from the 2 uF load.
  3. The original TVS standoff was below the 60 V operating maximum. The TVS and bulk capacitors were upgraded.
  4. The latch power-up state was not guaranteed. A voltage supervisor was added to force a safe startup inhibit.
  5. The hardware shutdown path was traced from current sensing through comparators, fault logic, GATE_ENABLE, STM32 TIM1_BKIN, and gate-driver inputs.
Phase 4: PCB Setup and Placement
A 180 mm x 200 mm four-layer PCB was configured. Components were grouped by function. The power section was arranged around a direct J1 -> F1 -> precharge/Q7 -> DC_BUS -> half-bridges -> motor output flow.
The three half-bridges were aligned, shunts were placed near their low-side MOSFETs, and gate drivers were moved outside major high-current copper corridors. Footprint corrections were applied to MOSFET drain copper, test points, and U8's exposed pad.
Phase 5: High-Current Routing
The layout uses project-specific high-current targets:
  • At least 5 mm for DC input, fused DC, DC bus, and primary PGND where geometry permits
  • At least 4 mm for motor phases and shunt-current paths
  • 2 mm for precharge branches and approved pad neckdowns
  • 0.5 mm clearance for the high-current groups
Completed work includes the 5 mm J1-to-F1 path, Q7 drain-entry repair, F1-to-Q7 routing, major DC-bus and PGND trunks, several phase and shunt paths, and removal of a real PGND-to-PH_W short.
Phase 6: Gate-Driver Cells
U2, U3, and U4 required local redesign to achieve compact gate and bootstrap loops. U2's low-side return was reduced from approximately 121 mm to 22.4 mm and connected to the PGND side of RS1 without bypassing the shunt. U3 and U4 received comparable dedicated local returns to the correct RS2 and RS3 terminals.
Phase 7: Current-Sense Cells
U- and W-phase sensing were completed and independently reviewed locally. The channels use terminal-origin Kelvin connections and were checked for shunt bypasses. The V-phase cell was relocated near RS2 and substantially routed; later routing connected additional ISENSE_V destinations.
Phase 8: Shutdown and Precharge Routing
The protection-routing phase completed major portions of:
  • Six comparator paths
  • ACTIVE_FAULT_N
  • Emergency stop
  • Fault latch and qualified reset
  • GATE_PREREQ and GATE_ENABLE
  • STM32 PA6/TIM1_BKIN
  • Six raw-to-gated PWM paths
  • Precharge divider and validity paths
  • LTC7001/Q7 gate actuation
  • Startup supervisor
The latest PCB state has 206 airwires, 194 redundant copper objects in 63 groups, 19 via-in-pad findings, and zero overlapping-copper findings. Remaining critical work includes U24 supply/return completion and DC-bus regulator routing.
Phase 9: Results and Analysis
The project has demonstrated successful design iteration, but not a completed physical VFD. The strongest verified results are:
  • Schematic ERC is clean.
  • Hardware current limits calculate to -12.004 A and +12.004 A.
  • The USB-side ground remains intentionally isolated from PGND.
  • The high-current input and precharge-bypass topology preserve distinct FUSED_DC and DC_BUS nets.
  • Local U2/U3/U4 gate-driver cells were substantially verified.
  • U- and W-phase Kelvin sensing were verified locally without shunt bypass.
  • Multiple PCB shorts, stale traces, pad-access problems, and long return paths were found and corrected.
The main result at this stage is a thoroughly developed and reviewed prototype design, not fabricated or tested hardware. No statement of working motor operation should be made until routing, DRC, assembly, bring-up, and load testing are complete.
Add the following evidence to the online report:
  1. System block diagram
  2. Full schematic overview
  3. Cropped inverter and gate-driver schematic
  4. Hardware fault and precharge schematic
  5. Full PCB layout screenshot
  6. Close-up of the three half-bridges and high-current copper
  7. U2 return-path comparison before and after correction
  8. U/W Kelvin-sense close-ups
  9. DRC and airwire-count screenshots
  10. Future oscilloscope captures of PWM, dead time, fault shutdown, and motor current
  11. Short bring-up and demonstration videos after assembly

6. System Block Diagram

Diagram


"48-60 V DC Input" "Fuse and TVS Protection" "Precharge Resistors and Q7 Bypass" "DC Link Capacitors and Bus Sensing" "Six-MOSFET Three-Phase Bridge" "Three-Phase Motor or RL Test Load" "Auxiliary Power Conversion" "12 V Gate Supply" "5 V Analog and Interface Rail" "3.3 V Logic Rail" "STM32G474 Control" "Raw PWM and Hardware Enable Logic" "Three Half-Bridge Gate Drivers" "Three Phase Shunts" "INA240 Current-Sense Amplifiers" "Positive and Negative Current Comparators" "Fault Combine, E-Stop, Latch, Reset" "Fused-Side and Bus-Side Dividers" "Precharge Valid Comparator and LTC7001" "USB-C, CP2102N, and ISO7721" "Start, Stop, Direction, Speed, Reset" "Telemetry and Status Outputs"
Block Explanations

Table


BlockPurposeMain components
Input and protectionAccepts low-voltage DC and limits fault/transient energy.J1, F1, D1, C1-C7
PrechargeLimits capacitor charging current and bypasses resistors after qualification.R67-R70, Q7, U25, C76, C77
DC linkStores energy and supplies the inverter bridge.C1-C7, C53, C61, C64
Three-phase bridgeConverts DC into PWM phase voltages.Q1-Q6
Gate driveLevel-shifts and drives high-side/low-side MOSFET gates.U2-U4, bootstrap capacitors, gate resistors
Current sensingMeasures each phase current.RS1-RS3, U5-U7, filters
Hardware protectionDetects overcurrent and disables all PWM independently of firmware.U19, U20, U21-U24, U15-U17
MCU controlGenerates PWM and supervises startup, faults, measurements, and communication.U1 STM32G474RET6
Auxiliary powerProduces 12 V, 5 V, and 3.3 V rails.U8-U10, L1, L2
USB isolationProvides laptop communication while separating ground domains.J3, D2, U12, U13
User controlsProvides commands, reset, programming, and status.J4-J6 and associated circuitry

7. Project Requirements and Engineering Specifications

Table


IDRequirementEngineering specificationCurrent verification method/status
R1Operate as a low-voltage three-phase inverter48 V nominal, 60 V maximum DC busSchematic/layout requirement established; energized test pending.
R2Support 1 hp motor-development architecture230 V, 1 hp motor is the final target; first board is a low-voltage validation platformArchitecture documented; full-voltage operation is outside current revision.
R3Control output frequency0-60 Hz open-loop V/HzFirmware implementation pending.
R4PWM switching20 kHz complementary PWM with dead timeMCU/gate hardware selected; oscilloscope validation pending.
R5Continuous phase current target5 A RMSCopper/shunt/component review in progress; load test pending.
R6Short peak-current target10 AComponent and shunt ratings selected; transient test pending.
R7Independent overcurrent tripNominal -12.004 A and +12.004 A on every phaseCalculations verified; injected-fault test pending.
R8Emergency shutdownNormally closed E-stop included in hardware fault pathSchematic and substantial PCB routing complete; bench test pending.
R9Hardware PWM shutdownDisable all six PWM paths and assert STM32 TIM1_BKINSchematic verified; final full-board continuity and bench test pending.
R10PrechargeInitial current through four 100 ohm resistors; Q7 bypass after about 91 percent bus chargeTopology and major routing complete; timing and failed-precharge tests pending.
R11Ground isolationLaptop USB_GND must not connect to GND or PGNDArchitecture maintained; final active-copper isolation test pending.
R12Auxiliary rails12 V gate rail, 5 V analog/interface rail, 3.3 V logic railRegulators selected; PCB completion and load testing pending.
R13Safe startupPower-up must default to gate-inhibited/faulted stateTLV803EA30 supervisor added; physical and timing test pending.
R14PCB construction180 mm x 200 mm, four copper layersImplemented.
R15High-current copper5 mm DC/PGND and 4 mm phase targets where geometry permitsRules established and partially implemented.
R16CommunicationIsolated USB serial command and telemetryHardware included; routing/firmware/test pending.
R17Stop behaviorCoast-to-stopSelected; firmware test pending.

8. Success Criteria and Test Plan
8.1 Overall Success Criteria
The low-voltage prototype will be considered successful when:
  • All required PCB nets are routed with zero functional airwires.
  • All blocking DRC errors are cleared.
  • USB ground isolation and FUSED_DC/DC_BUS separation are proven.
  • Auxiliary rails start correctly under current-limited power.
  • PWM frequency, complementary timing, and dead time meet the design target.
  • Any overcurrent comparator, E-stop, or startup fault disables all six gate commands and asserts timer break.
  • Precharge limits inrush and Q7 bypass activates only after the bus reaches the required ratio.
  • The inverter produces ordered three-phase waveforms into a passive RL load.
  • A low-voltage motor follows the commanded frequency without unsafe current or temperature rise.
8.2 Requirement Test Matrix

Table


TestProcedureDataset sizePass criterion
PCB continuityMeasure power and signal nets before power-up.100 percent of power rails, phase nodes, safety nets, and connector pinsNo unintended shorts; intended continuity present.
USB isolationMeasure resistance between USB_GND, GND, and PGND.3 domain pairs, repeated before and after assembly cleaningNo DC connection across the intended isolation barrier.
Auxiliary railsApply current-limited DC input at several voltages and loads.5 input voltages x 3 load conditions per railRails remain within +/-5 percent with no thermal fault.
PWM and dead timeObserve all six gate commands and representative gate voltages.6 channels at 5, 20, 40, and 60 Hz command20 kHz carrier, no overlap, dead time meets firmware target.
Current-sense calibrationApply known bidirectional shunt current.At least 11 points from -10 A to +10 A per channelGain and offset within the selected tolerance; monotonic response.
Overcurrent shutdownInject equivalent sense voltages across each high/low comparator.6 comparator paths x 5 repetitionsAll gates disabled and fault latched every time.
E-stopOpen the normally closed E-stop circuit during idle and PWM operation.10 repetitions in each conditionImmediate gate disable; restart requires qualified reset.
Startup inhibitCycle power at minimum, nominal, and maximum test input.10 cycles at each voltageGate enable remains low until supplies, precharge, and reset conditions are valid.
PrechargeRecord input current and bus voltage during startup.10 startups at 24 V, 48 V, and 60 V if safeNo direct bypass before valid; bus reaches threshold; Q7 activates correctly.
Failed prechargePrevent bus rise or disable Q7 command.5 trials per fault modeGate enable remains inhibited; resistor temperature remains safe for test duration.
RL-load outputOperate into a balanced three-phase RL load.5, 10, 20, 40, and 60 Hz; 3 load levelsBalanced phase order, controlled current, no protection nuisance trips.
Motor testRun a low-voltage-compatible motor or reduced-voltage test setup.Minimum 5 frequencies and 3 load pointsMotor follows command; current and temperatures remain within limits.
Thermal testMonitor MOSFETs, shunts, drivers, regulators, and precharge resistors.30-minute run at each major load pointNo part exceeds its approved temperature limit.
8.3 Safety Limitation
The present PCB must not be energized while required airwires, safety-critical opens, or blocking DRC findings remain. Testing begins only after an independent pre-power review.

9. Power Tree and Power Budget
9.1 Power Tree

Diagram


"48-60 V DC Bus" "Three-Phase Inverter Power Stage" "U8 High-Voltage Buck to 12 V" "Three Gate Drivers and Q7 Driver" "U9 Buck to 5 V" "INA240 Current-Sense Amplifiers and Analog Circuits" "U10 LDO to 3.3 V" "STM32, Logic, Comparators, and Controls" "USB-C 5 V" "CP2102N and USB Side of Isolator" "Galvanic Digital Isolation"
9.2 Preliminary Control-Power Budget
The following values are design estimates and must be replaced or confirmed with measured current during bring-up.

Table


RailMajor loadsPreliminary design allowance
12 VU2-U4 gate drivers, U25 Q7 driver, switching losses0.5-0.8 A peak allowance
5 VU5-U7 current-sense amplifiers, analog support, regulator overhead0.2-0.3 A allowance
3.3 VSTM32, comparators, logic, controls, status circuits0.15-0.25 A allowance
USB 5 V isolated sideCP2102N and USB side of ISO7721Less than 0.1 A expected
At 60 V input, a conservative 12 W auxiliary-power allowance corresponds to approximately 0.2 A from the DC bus before including inverter output power. The inverter power path dominates total input power. At the prototype target of 5 A RMS phase current, actual DC input current depends on output voltage, load power factor, modulation index, switching losses, and motor efficiency and must be measured during staged load tests.
9.3 Power-Path Rating Notes
  • Q1-Q7 are 150 V MOSFETs for the 60 V prototype.
  • The bulk capacitors were upgraded to 100 V after TVS coordination review.
  • The TVS must remain nonconducting at the 60 V maximum normal bus.
  • The 5 milliohm, 3 W shunts dissipate 0.125 W at 5 A and 0.5 W at 10 A, excluding pulse and local thermal effects.
  • Each 100 ohm precharge resistor initially sees approximately 36 W at 60 V if the four resistors are configured as parallel paths; startup duration and pulse-energy capability must be validated.
  • Final power-budget approval requires regulator efficiency, inductor saturation, gate-charge, capacitor ripple-current, and thermal measurements.

10. Ten-Week Proposed Timeline

Table


WeekPlanned activitiesDeliverable or milestone
1Freeze requirements, architecture, component list, preliminary budget, and risk plan. Begin ordering long-lead parts.Approved proposal, block diagram, initial BOM, orders placed.
2Complete schematic and protection calculations. Review datasheets and ERC.Schematic review package and corrected calculations.
3Complete PCB placement, footprint checks, stackup, and design rules.Placement review and routing-ready board.
4Route input, DC bus, PGND, motor phases, precharge, gate loops, and current sensing.Critical power and analog routing complete.
5Route protection, MCU, auxiliary rails, USB, and controls. Clear airwires and blocking DRC.Fabrication-ready PCB release.
6Receive parts/PCB, assemble, inspect, and perform unpowered checks. Continue firmware development.Assembled board and inspection record.
7Bring up auxiliary rails, MCU, SWD, USB, ADCs, and basic PWM without energizing the bridge.Low-energy bring-up report.
8Validate gate waveforms, dead time, E-stop, overcurrent, startup inhibit, and precharge.Safety and gate-drive test results.
9Test with passive RL load, then reduced-voltage motor if all protections pass. Collect current and thermal data.Controlled inverter operation and waveform evidence.
10Complete motor demonstration, analyze results, finalize budget, report, website, presentation, and video.Final demonstration and submission package.
Procurement Timing
Order immediately after exact MPN and footprint verification:
  • STM32G474RET6
  • UCC27211AQDDARQ1
  • BSC074N15NS5
  • INA240A1D
  • LTC7001IMSE#TRPBF
  • LM5164DDA and regulator inductors
  • DC-link capacitors and film capacitor
  • Fuse and terminal blocks
  • USB-C, CP2102N, ISO7721, and ESD array
  • Shunts and precharge resistors
Do not place the final PCB fabrication order until routing and DRC pass. Long-lead components may be ordered earlier if their footprints and exact MPNs are frozen.

11. Proposed Versus Actual Timeline

Table


ActivityProposed completionActual status as of Sept. 30, 2026Variance and reason
Requirements and architectureWeek 1CompletedOn scope.
Schematic and calculationsWeek 2Substantially completed; ERC cleanAdditional protection corrections extended this phase.
Placement and rulesWeek 3Completed with repeated footprint correctionsMore custom pad reconciliation than expected.
Critical routingWeek 4Partially completedGate loops, Kelvin routes, stale copper, and custom pads required repeated local redesign.
Full PCB releaseWeek 5Not completed206 airwires, redundant copper, via-in-pad findings, U24 and regulator opens remain.
ProcurementWeeks 1-5Draft BOM completed; final order readiness incompleteGeneric passive MPNs and several sourcing risks remain.
FirmwareWeeks 3-7Planned but not completedPCB safety and routing work took priority.
AssemblyWeek 6Not startedPCB has not been released.
Bring-up and protection testsWeeks 7-8Not startedRequires assembled, reviewed board.
Load and motor testsWeeks 9-10Not startedDependent on successful bring-up.
Final reportWeek 10In progressDesign evidence and honest limitations documented.

12. Detailed Bill of Materials
12.1 BOM Summary
The earlier procurement extraction contained 193 purchasable instances across 35 part groups. The latest schematic contains 215 components because the protection update added a startup supervisor and associated support circuitry. The official BOM must be regenerated after PCB completion.
12.2 Major Components

Table


QtyReferencesComponent / MPNFunctionStatus
1U1STM32G474RET6Main motor-control MCUSelected
3U2-U4UCC27211AQDDARQ1Half-bridge gate driversSelected
7Q1-Q7BSC074N15NS5150 V power MOSFETsSelected
3U5-U7INA240A1DPhase-current amplifiersSelected
3RS1-RS3HoJLR2512-3W-5mR-1%5 milliohm shuntsManufacturer verification required
1U8LM5164DDA60 V bus to 12 V regulatorSourcing verification required
1U9LMR50410Y5FQDBVRQ112 V to 5 V regulatorSelected
1U10TPS7A2033PDBVR5 V to 3.3 V LDOSelected
1U11TMP235A2DCKRTemperature sensorStock/alternate review required
1U12CP2102N-A02-GQFN24USB-UART bridgeSelected
1U13ISO7721DRDigital isolatorSelected
3U15-U17SN74LVC2G08DCURDual PWM gate logicSelected
2U19-U20TLV9024PWRQuad comparatorsSelected
1U21SN74LVC1G74DCTRFault latchSelected
1U22SN74LVC1G07QDBVRQ1Open-drain fault combineSelected
1U23SN74LVC1G00DBVRG4Reset qualification logicActive suffix review required
2U14, U24SN74LVC1G11DBVRG4Three-input gate-enable logicActive suffix review required
1U25LTC7001IMSE#TRPBFQ7 high-side driverLong-lead item
1Startup supervisorTLV803EA30DBZRDeterministic power-up inhibitAdded in latest revision
1D11.5SMC75A classDC-bus TVSUpdated; exact orderable MPN to freeze
2C1, C2UCY2C471MHD class470 uF, 100 V bulk capacitorsUpdated
1C4ECW-F2105JAQ1 uF, 250 V film capacitorAlternate sourcing may be required
4C3, C5-C7C3216X7R2A105K160AA1 uF, 100 V ceramicsSelected
4R67-R70AC05000001000JAC00100 ohm, 5 W precharge resistorsSelected
1F10476012.MRSN12 A DC fuseInterrupt rating review required
1J11714971DC input terminalSelected
1J2691137710003Motor output terminalRating/mating review required
1J3USB4105-GF-AUSB-C connectorSelected
1J4FTSH-105-01-X-DV-K-XSWD headerExact ordering code required
1J5Unassigned 1x8 headerLocal controls/statusExact MPN required
1J615ETYRM-3.5-02P-14-00AHE-stop terminalStocked alternate may be required
1D2SP0503BAHTGUSB ESD protectionManufacturer/footprint verification required
2D3, D4BAT54S-TPSchottky clampsSelected
12.3 Generic Passive Groups Requiring Exact MPNs

Table


GroupApproximate quantityRequirements
Generic resistors66 in the earlier BOMConsolidate by value, package, tolerance, power, voltage, and pulse rating.
Generic capacitors69 in the earlier BOMAssign X7R/C0G dielectric, tolerance, voltage rating, DC-bias allowance, and MPN.
Generic inductors2L1: 68 uH, saturation at least 1.8 A; L2: 4.7 uH, saturation at least 1.5 A. Verify DCR and thermal rise.
  • Order 9-10 MOSFETs for seven installed positions.
  • Order installed IC quantity plus one spare for each unique active device.
  • Order at least 20 percent extra for 0603/0805 passives, with a minimum of 10 pieces per line.
  • Order one spare for each unique fuse, shunt, DC-link capacitor, connector, and power resistor.
  • Order 2.2 ohm, 4.7 ohm, and 10 ohm gate-resistor alternatives for tuning.
12.5 Procurement Release Blockers
  • Regenerate the BOM after the latest schematic additions.
  • Assign exact MPNs to generic passives and inductors.
  • Resolve C4, U8, U11, U14/U24, U23, U25, F1, J4, J5, J6, and D2 sourcing questions.
  • Verify fuse interrupt rating, connector current rating, inductor saturation, capacitor ripple current, and MOSFET thermal performance.
  • Complete routing and final DRC before ordering the PCB.

13. Proposed and Actual Budget
Exact purchase prices and receipts are not present in the design records. The following table is a submission-ready budget worksheet; enter quoted and paid amounts before final submission.

Table


CategoryProposed budgetActual costNotes
PCB fabrication, 4-layer prototypesTBDTBDInclude shipping and stencil if used.
STM32 and control ICsTBDTBDInclude one spare MCU.
MOSFETs and gate driversTBDTBDInclude spare MOSFETs and gate-resistor options.
Current sensing and protectionTBDTBDShunts, INA240s, comparators, logic, supervisor.
Auxiliary power suppliesTBDTBDRegulators, inductors, diodes, and capacitors.
DC-link and precharge partsTBDTBDBulk/film capacitors, fuse, TVS, Q7, driver, resistors.
USB, isolation, and connectorsTBDTBDUSB-C, CP2102N, ISO7721, ESD, headers, terminals.
Generic passivesTBDTBDConsolidated resistor/capacitor lines plus spares.
Assembly suppliesTBDTBDSolder paste, flux, stencil, wire, terminals, hardware.
Test equipment or fixturesTBDTBDRL load, current probe access, insulated leads, enclosure/guards.
TotalTBDTBDAttach distributor quotes and receipts.

14. Risk Assessment and Mitigation

Table


RiskImpactMitigation
Energizing an incomplete boardComponent damage or unsafe behaviorDo not power until zero required airwires, blocking DRC cleared, and independent pre-power review completed.
Overcurrent protection failureMOSFET or load damageVerify every sensor-to-gate shutdown path and perform injected-fault tests before load testing.
Precharge bypass errorHigh inrush currentPreserve distinct FUSED_DC/DC_BUS nets and verify resistor/Q7 paths physically.
Ground-isolation failureLaptop or equipment damageResistance and active-copper inspection between USB_GND and PGND/GND.
Gate-loop inductanceRinging or false turn-onCompact local cells, short gate returns, adjustable gate resistors, oscilloscope validation.
Shunt bypass or poor Kelvin pickupIncorrect current measurementTerminal-origin Kelvin routing and copper-bypass inspection.
Component sourcing changesFootprint or rating mismatchFreeze exact MPNs before fabrication and check all alternates against pinout and footprint.
Thermal overloadReduced reliability or failureStaged current tests and temperature monitoring before full-duration operation.
Schedule delayIncomplete demonstrationPrioritize a safe low-voltage demonstration; defer full-voltage scope and nonessential features.

15. Documents and Supporting Records
The project records include:
  • Project specification
  • System block diagram
  • Component-selection and power-budget analysis
  • Protection-circuit datasheet verification
  • Schematic net reconciliation
  • Procurement BOM
  • PCB routing-readiness review
  • Gate-driver verification records for U2, U3, and U4
  • U-, V-, and W-phase current-sense reports
  • Routing-recovery report
  • Protection and startup-inhibit review
  • Five-day and capstone progress reports
Recommended submission attachments:
  • Proposal report
  • Current schematic PDF
  • Current PCB screenshots
  • Consolidated BOM spreadsheet
  • Relevant component datasheets
  • Test plan
  • Risk assessment
  • Distributor quotes and receipts
  • Firmware source and README when available
  • Bring-up data, plots, images, and videos when available

16. Citations and References
Use bracketed references in the website text, for example: The STM32G474 includes advanced motor-control timers with break inputs [1].
  1. STMicroelectronics, STM32G474xx Mixed-Signal Microcontroller Datasheet and Reference Manual.
  2. Texas Instruments, UCC27211A-Q1 120-V Half-Bridge Gate Driver Datasheet.
  3. Infineon Technologies, BSC074N15NS5 150-V OptiMOS MOSFET Datasheet.
  4. Texas Instruments, INA240 Enhanced PWM Rejection Current-Sense Amplifier Datasheet.
  5. Texas Instruments, TLV9024 Quad Nanopower Comparator Datasheet.
  6. Analog Devices, LTC7001 Fast High-Side N-Channel MOSFET Static Switch Driver Datasheet.
  7. Texas Instruments, LM5164 100-V Synchronous Buck Converter Datasheet.
  8. Texas Instruments, LMR50410-Q1 Buck Converter Datasheet.
  9. Texas Instruments, TPS7A20 Low-Noise LDO Datasheet.
  10. Silicon Labs, CP2102N USB-to-UART Bridge Datasheet.
  11. Texas Instruments, ISO7721 High-Speed Digital Isolator Datasheet.
  12. Littelfuse, 1.5SMC Series Surface-Mount TVS Diode Datasheet.
  13. Texas Instruments, TLV803E Supply-Voltage Supervisor Datasheet.
  14. IEC 61800-5-1, Adjustable Speed Electrical Power Drive Systems - Safety Requirements.
  15. IPC-2221, Generic Standard on Printed Board Design.
  16. IPC-2152, Standard for Determining Current-Carrying Capacity in Printed Board Design.
  17. Project schematic, layout, BOM, and engineering review records, revision current as of September 30, 2026.
Before submission, replace generic datasheet titles with full bibliographic entries or direct manufacturer URLs in the website reference list. Ensure every technical claim that depends on a datasheet includes the matching bracketed reference number.

17. Current Conclusion
The project has successfully produced a detailed low-voltage VFD architecture, clean schematic ERC, corrected hardware current protection, deterministic startup inhibit, a coordinated TVS/bulk-capacitor strategy, three gate-driver cells, phase-current sensing, substantial high-current routing, precharge control, and isolated communication architecture.
The design process also identified and corrected defects that could have caused unsafe or nonfunctional behavior. These included incorrect current thresholds, an overloaded reference node, a TVS with inadequate standoff, uncertain power-up latch behavior, a PGND-to-phase short, excessive gate-return length, defective footprint copper, and potential shunt bypass paths.
The project is not yet a working assembled VFD. The PCB still has 206 airwires, 194 redundant copper objects, 19 via-in-pad findings, and remaining safety-critical U24 and regulator connections. Fabrication, assembly, firmware completion, bring-up, and motor testing remain future work. The appropriate final demonstration target is a safe 48-60 V prototype, not direct operation from rectified 230 VAC.
The remaining path is clear: finish functional routing, remove proven stale copper, clear blocking DRC, freeze the BOM, fabricate and assemble the board, validate protection at low energy, test with an RL load, and then perform a reduced-voltage motor demonstration.
  • 1. Landing Page: Abstract, Explanation, and Motivation

  • Abstract

  • Project Motivation

  • 2. Design Proposal and Design Ideas Considered

  • 2.1 Selected Design

  • 2.2 Design Alternatives Considered

  • 2.3 Important Design Changes During Development

  • 3. Group Member Biography and Responsibilities

  • Harvey Tada

  • 4. Time and Effort Table

  • 5. Project Progress Log

  • Phase 1: Requirements and Architecture

  • Phase 2: Schematic Development

  • Phase 3: Protection Corrections

  • Phase 4: PCB Setup and Placement

  • Phase 5: High-Current Routing

  • Phase 6: Gate-Driver Cells

  • Phase 7: Current-Sense Cells

  • Phase 8: Shutdown and Precharge Routing

  • Phase 9: Results and Analysis

  • Recommended Figures and Videos for the Website

  • 6. System Block Diagram

  • Block Explanations

  • 7. Project Requirements and Engineering Specifications

  • 8. Success Criteria and Test Plan

  • 8.1 Overall Success Criteria

  • 8.2 Requirement Test Matrix

  • 8.3 Safety Limitation

  • 9. Power Tree and Power Budget

  • 9.1 Power Tree

  • 9.2 Preliminary Control-Power Budget

  • 9.3 Power-Path Rating Notes

  • 10. Ten-Week Proposed Timeline

  • Procurement Timing

  • 11. Proposed Versus Actual Timeline

  • 12. Detailed Bill of Materials

  • 12.1 BOM Summary

  • 12.2 Major Components

  • 12.3 Generic Passive Groups Requiring Exact MPNs

  • 12.4 Recommended Spare Quantities

  • 12.5 Procurement Release Blockers

  • 13. Proposed and Actual Budget

  • 14. Risk Assessment and Mitigation

  • 15. Documents and Supporting Records

  • 16. Citations and References

  • 17. Current Conclusion