Five-Day Progress Report
Project: 1 HP Three-Phase Variable-Frequency Drive
Reporting period: September 5–9, 2026
Prepared: September 10, 2026
Current prototype scope: 48 V nominal, 60 V maximum DC bus; 5 A RMS phase current; 10 A short peak; 20 kHz complementary PWM
Executive Summary
During this five-day period, the project advanced primarily through PCB power-stage placement refinement, routing-rule preparation, high-current routing experiments, correction of the precharge-bypass MOSFET routing geometry, USB-C differential-pair breakout work, and creation of a procurement-oriented bill of materials. The most important verified routing achievement was repairing the Q7 drain-pad access and completing the fused-input connection from F1 to Q7 using a short 2 mm neckdown into a 5 mm high-current trunk.
The PCB is not yet complete or ready for fabrication. The schematic architecture and protection functions remain established, but the majority of the DC bus, phase, shunt, ground, gate-drive, control, and auxiliary routing is unfinished. The detailed project history contains recorded layout activity on September 8 and BOM documentation on September 9; no committed project mutations were recorded for September 5–7.
September 5–7: Planning and Routing Preparation
No committed schematic, PCB, or project-file changes were recorded in the project history on these dates. Work during this portion of the reporting window centered on identifying the next critical tasks and defining the correct execution order:
- Optimize the physical power-stage arrangement before extensive routing.
- Preserve the verified 48–60 V prototype architecture rather than expanding to the future high-voltage stage.
- Route the power system in the order of input, fuse, precharge/bypass, DC link, half bridges, phase outputs, shunts, and PGND.
- Resolve pad-mapping and routing-access problems before allowing automated routing to operate across the board.
- Retain galvanic separation between the laptop-side USB ground and the inverter control/power ground domains.
This preparation was important because earlier board-wide routing attempts had stalled or produced geometries that conflicted with existing copper.
September 8: PCB Placement and Routing Work
Power-Stage Placement Refinement
The power-stage area was reorganized to create clearer current-flow corridors. Recorded component-position changes affected the input/precharge region, the three inverter half bridges, the current shunts, the gate-driver region, and nearby support components.
The intended physical current flow was organized as:
DC input → input fuse → precharge resistor/bypass network → DC-link capacitors → three inverter half bridges → phase-current shunts and motor output
The three MOSFET half bridges were aligned more consistently, and their associated shunts and gate-drive support areas were positioned to support short power and gate-current paths. Additional targeted moves were made around the precharge-bypass device to improve routing access.
Layout-Rule Refinement
Layout rules were adjusted repeatedly to support the high-current power paths and dense component pads. The routing strategy retained:
- 5 mm primary DC and PGND trunks.
- 4 mm phase and shunt-current paths.
- 2 mm permitted neckdowns in the precharge/DC-bus region where pad geometry prevents direct 5 mm entry.
- 0.5 mm high-current clearance targets.
The repeated rule edits were part of an iterative route-check-correct cycle rather than changes to the electrical architecture.
Q7 Drain-Pad Routing Repair
The principal upstream routing blocker was the terminal-bound drain geometry of Q7, the precharge-bypass MOSFET. The original pad mapping retained valid thermal copper but did not provide usable routing access for the required high-current connection.
The repair enlarged the terminal-bound drain routing envelope to approximately 4.70 mm × 5.08 mm while preserving the required physical offset and FUSED_DC connectivity. The overlapping unbound duplicate copper remained disabled so only the verified terminal-bound physical land was active.
This corrected the footprint’s routing-entry problem without replacing the MOSFET or altering the precharge topology.
F1-to-Q7 High-Current Route
After the Q7 geometry repair, the fused-input path was completed using:
- A short 2 mm-wide neckdown, approximately 0.87 mm long, at the pad entry.
- A 5 mm-wide trunk, approximately 6.28 mm long, for the main current path.
This route connects the input fuse output to the precharge-bypass MOSFET while returning to the preferred 5 mm width immediately after the constrained pad entry.
The existing J1-to-F1 input path remained part of the verified input corridor. Earlier conflicting or incomplete trace experiments were deleted or reverted rather than left as ambiguous copper.
Neckdown Generation and Routing Iterations
Automated neckdown generation was applied across several dense nets, including power, phase, shunt, ground, and supply connections. Numerous trace additions, deletions, routing attempts, and one single-commit revert were recorded while evaluating feasible paths.
Unsuccessful or conflicting copper was removed. This prevented failed routing experiments from becoming permanent short-circuit or floating-copper risks.
USB-C Differential Breakout
The two trace groups initially reported as dangling were identified as protected USB-C differential-pair escape stubs rather than stale copper. The USB-C breakout was regenerated so the D+ and D− connections retained protected, coupled escape geometry.
The breakout work generated protected routing segments with no failed pair nets. A residual routing-check warning remains associated with the connector’s duplicated physical D+/D− pads, but the breakout geometry itself was preserved instead of being deleted as stale copper.
Verification Results
Following the focused Q7 and input-path work, independent checks reported no:
- Different-net copper overlaps.
- Floating copper associated with the corrected route.
- Pad-access errors.
- Component body overlaps.
- Out-of-bounds components.
- Keepout violations.
- Invalid copper layers.
Remaining advisories included intentional same-net merged MOSFET pads and via-at-SMD conditions associated with dense/exposed-pad components. These require final review but were not identified as different-net short circuits.
September 9: Procurement BOM Development
A procurement-oriented BOM was created from the live schematic. The extracted BOM contains:
- 193 purchasable component instances.
- 35 grouped part lines.
- 66 generic resistors.
- 69 generic capacitors.
- 2 generic inductors.
The BOM identifies the major MCU, gate drivers, MOSFETs, current-sense amplifiers, shunts, regulators, protection devices, DC-link capacitors, precharge resistors, logic devices, isolation components, and connectors.
The report also consolidates passive values and package requirements and identifies sourcing risks. Important procurement blockers include:
- Exact manufacturer part numbers are not yet assigned to all generic resistors, capacitors, and inductors.
- Several components have limited, inconsistent, or ambiguous availability.
- Some connector lines still require exact mating plugs, housings, or orderable suffixes.
- Final purchasing quantities should not be frozen until PCB routing and footprint verification are complete.
Current Project Status at the End of the Period
Completed or Substantially Completed
- System architecture and 48–60 V prototype limits defined.
- STM32G4 controller, three half-bridge drivers, six-switch inverter, current sensing, auxiliary power, isolated USB, and hardware protection included in the schematic.
- Hardware overcurrent, E-stop, fault latch, reset qualification, gate-enable logic, and precharge-valid architecture established.
- PCB board size, stackup, broad placement, and high-current routing rules established.
- Major footprint conflicts involving MOSFET power pads, test points, the regulator exposed pad, and overlapping capacitors previously corrected.
- Power-stage placement refined for clearer current flow.
- Q7 drain routing access repaired.
- J1-to-F1 input corridor retained and F1-to-Q7 route verified.
- USB-C differential breakout regenerated and protected.
- Procurement BOM created with sourcing and MPN-assignment risks documented.
Incomplete
- DC_BUS distribution from the precharge/bypass network to the DC-link capacitors and all three high-side MOSFETs.
- Complete resistor-bank precharge routing and physical proof that no unintended copper bypasses both Q7 and the resistor bank.
- Main PGND network.
- PH_U, PH_V, and PH_W motor-current paths.
- Low-side MOSFET-to-shunt paths.
- Kelvin current-sense routing.
- Gate-driver output and bootstrap loops.
- Auxiliary rails, MCU signals, hardware-fault signals, and general control routing.
- Final USB differential routing beyond the protected connector breakout.
- Airwire elimination and complete PCB DRC.
- Thermal/current-density review and manufacturing export.
- Firmware, HMI, board assembly, bring-up, fault injection, RL-load testing, and motor testing.
Problems Encountered and Corrective Actions
Board-Wide Routing Processes Stalled
Several broad routing attempts stopped before completing or producing a reliable report. The corrective action was to stop treating the PCB as one large routing job and divide it into deterministic subsystems. The current strategy is to complete and verify the input/precharge path first, followed by DC bus, PGND, phases, shunts, gate loops, sensing, controls, and USB.
High-Current Route Conflicts
Initial attempts to route the fuse, bypass MOSFET, and DC-link capacitor corridor created overlap conflicts or no-path results. Failed copper was removed. The root cause was traced to Q7’s pad-entry geometry rather than ordinary component congestion, and the terminal-bound pad was repaired.
Apparent Dangling USB Traces
Two routing groups appeared to be dangling traces. Inspection showed that they were protected USB-C differential breakout stubs. They were regenerated and retained so that cleanup did not damage the high-speed connector escape.
Priorities for the Next Work Period
- Route and verify the complete precharge resistor path in parallel with Q7, using distinct source-side and capacitor-side nets.
- Complete the 5 mm DC_BUS distribution to the bulk capacitors and the three high-side switches.
- Complete the 5 mm PGND structure and the 4 mm phase/shunt current paths.
- Route gate-drive loops and bootstrap capacitors with minimum loop area.
- Route Kelvin sense pairs independently from load-current copper.
- Connect the protected USB-C breakout to the USB-UART interface using controlled differential routing.
- Route remaining auxiliary and logic nets, then eliminate all airwires.
- Run full routing preflight, DRC, connectivity, thermal, isolation, and protection-path reviews.
- Assign exact MPNs to every generic passive and inductor, then export the assembly BOM and manufacturing package.
- Begin firmware and bring-up documentation in parallel with final PCB completion.
Conclusion
The past five days produced measurable progress on the most difficult physical-design blocker in the input/precharge region. The Q7 pad-access defect was corrected, a compliant fused-input route was established, protected USB-C escape routing was restored, and the project now has a structured procurement BOM. The board remains in the routing phase, with the DC bus and most supporting nets still incomplete. The next milestone is a fully connected high-current network with no unintended precharge bypass, followed by completion of sensitive routing and final DRC.