Test Rig Bring-Up Plan
Preconditions
- Inspect polarity/orientation of D1, D2, D3, D4, Q1, LED1, U2-U5.
- Verify no PCB layout has been started and use schematic/netlist for a carrier or hand-wired prototype review.
- Do not connect a real heater, cutoff, thermistor, thermocouple, or optical head initially.
- Fit a normally-closed jumper/bench switch at J4 only when actively testing; opening J4 must be the default safe action.
- Confirm F1 marking/lot is Littelfuse 02153.15MXEP, 3.15 A time-lag; do not substitute the former 2.5 A very-fast part.
1. Resistance and continuity checks — power off
- Confirm J1 pin 2 to TP4/GND continuity.
- Confirm J1 pin 1 reaches F1 then D1 but is not shorted to ground.
- Confirm
12V_PROTECTED, 5V_LOGIC, and 3V3 are not shorted to ground; record resistance after capacitors charge.
- Confirm J3 is the only series bridge between
12V_PROTECTED and J2 pin 1.
- Confirm Q1 source is ground and drain is J2 pin 2; verify Q1 gate is pulled low by R10.
- Confirm J4 open pulls
INTERLOCK_OK_5V low through R6.
- Confirm R25 measures approximately 10 kΩ from
HEATER_PWM_CMD to GND with U1 unpowered.
- Confirm J6 TC+ reaches U3
T+ only through R26 and J6 TC- reaches U3 T- only through R27 (approximately 100 Ω each). Confirm U3 BIAS is on connector-side TC_MINUS with J6 TC- and R27 pin 1, not on TC_MINUS_FILT. Confirm C9 is across TC_PLUS_FILT/TC_MINUS_FILT and C10/C11 connect those filtered nodes to ground.
Pass: no hard rail short; heater path and guard behavior match the net names.
2. Current-limited rail bring-up
- Remove U1 if socketed or leave USB disconnected. Set bench supply to 12.0 V, 100 mA limit.
- Apply power at J1. Verify polarity and measure TP1. Expect about 11.5-11.8 V after the Schottky under light load.
- Measure TP2: 5.0 V nominal. Measure TP3: 3.3 V only when U1 is installed.
- Check D1, F1, PS1, U4, and U5 for unexpected heating.
- Raise current limit to 300 mA only after rails pass.
Pass: 5 V within module tolerance, Pico 3.3 V normal, idle current plausible (=50 W load at J2. Start at 12 V with 0.5 A current limit.
3. Exercise 10%, 25%, 50%, and 100% duty while observing TP5, TP6, Q1 drain, input current, and Q1 temperature.
4. Raise current limit in stages to 2.0 A after waveforms are clean.
5. Open J4 at every duty setting and confirm load current stops.
Pass: current scales with duty, Q1 remains cool at steady full load, drain transient stays comfortably below 55 V, D4 does not overheat.
7. Real heater/block test
- Install the actual G4A00091C in the physical J3 loop using the intended mount and strain relief. Record part lot and mounting details.
- Connect heater at J2 and calibrated NTC at J5. Use current limit 0.5 A for wiring confirmation, then increase toward 2.0 A.
- Run a low-duty pulse, verify positive temperature response, then execute empty-block preheat.
- Compare input current to the expected 1.5-1.7 A at full duty; inspect connectors and wiring with thermal imaging.
- Run guarded hot insertion with a sealed water-filled engineering tube and thermocouple reference.
- Exercise thermocouple disconnect, short, intermittent contact, and stalled-DRDY cases at safe low power; every case must latch heater-off.
- Confirm equilibrium does not pass after an out-of-band sample, a >1.5 s logging gap, or a drifting trace with deceptively similar endpoints.
- In a deliberately shortened-timeout firmware build, confirm the active-cycle bound latches heater-off and preserves the fault reason/code. Restore and document the configurable 90-minute engineering default before normal experiments.
Pass: stable control without overshoot beyond the preliminary target; no connector/harness hotspot; plausible block/liquid offset.
8. Cutoff qualification
Use a dedicated, supervised setup and a fresh cutoff. Independently monitor temperature and current. Force a controlled overtemperature condition consistent with the qualification plan, verify irreversible opening, remove power, cool, and confirm it remains open. Do not bypass the guard except under the written qualification procedure.
Pass: heater current becomes zero and the cutoff remains electrically open after cooling. Record trip temperature, delay, mount, contact pressure, lot, and measurement uncertainty.
9. Optical head
- Confirm J7 module voltage and exact pin order before connection. Starter assumption is a 3.3 V TCS34725-compatible RGB/clear breakout.
- With J8 disconnected, verify all
LED_*_CMD and MOSFET gates default low.
- Connect one emitter at a time and verify current against R12-R15 and emitter forward voltage.
- Confirm DARK command leaves all emitters off; acquire dark samples with chamber open/closed.
- Run white/R/G/B sequencing, check sensor saturation, LED drift, ambient leakage, and tube reinsertion repeatability.
Pass: independent channels, no overlap, no overcurrent, dark acquisition works, and raw R/G/B/clear values are logged.
Stop/fail conditions
Stop immediately for rail overvoltage, smoke/odor, unexpected >2.2 A normal input, Q1/fuse/connector rapid heating, unstable temperature, inability of J4 or R25/reset state to force TP6 low, failure to detect stale/invalid sensors, startup open-circuit qualification failure, failure of the active-cycle timeout to latch heater-off, sensor wiring uncertainty, or any bypass of the physical one-shot cutoff outside a controlled dummy-load step.