JLCPCB Part Substitutions


Created a project doc

JLCPCB Shortfall Replacement Guide

View Document

JLCPCB Shortfall Replacement Guide Decision summary — 2026-10-15
This is sourcing advice for the seven entries in the uploaded shortfall list, not an updated BOM or fabrication approval. No schematic, footprint, routing, or BOM properties were changed. Stock observations are point-in-time public catalog/distributor results, not a reservation in your JLCPCB order; checkout availability wins. LCSC stock is explicitly distinguished from JLCPCB assembly stock below.
What to select for each item
The requested purchase quantities come from the user's pasted order screen, not a new assembly quantity calculation. JLCPCB may require additional pieces for assembly attrition. Keep any required extra quantity when rematching.
Why U1's suffix swap is safe
I saved the seven-part replacement list—with exact LCSC numbers, stock checks, and unresolved qualifications—in your project files: JLCPCB Shortfall Replacement Guide; the immediately stocked recommendations are R2 → C346633 and R3 → C2684521.
The guide gives exact alternatives for the feedback resistor and charger pending checkout availability, a conditional capacitor candidate, and recommends sourcing the original inductor and modem rather than an unverified swap; I haven’t changed your BOM or board.
Before releasing the order, request a fresh DRC/connectivity check: your latest saved checkpoint still flags copper overlaps and unrouted USB connections.
U6 and L2 not letting me to source
I’ll check alternatives for those two parts and JLCPCB’s sourcing restrictions; I won’t assume pre-ordering is available for your order.
My earlier pre-order suggestion wasn’t a confirmed purchasing route for your order, and I haven’t verified a safe, stocked drop-in for U6 or L2. JLCPCB distinguishes stock shortages, sourcing restrictions, and “Standard Only” assembly restrictions, so the exact message matters.
Can you share a screenshot of what appears when you try sourcing each part, and whether your order uses Economic or Standard assembly?

Waiting for input


PCB Layout Handoff
Purpose and release status
This document is the handoff for completing the PCB in another EDA tool. It combines the current live PCB state, the schematic design-review corrections, and the routing constraints established during the failed routing attempts.
Current status: not fabrication-ready. The latest live DRC snapshot (2026-08-13) reports 8 airwires. Manufacturing outputs must not be released until the schematic corrections are implemented, all eight connections are physically routed, the synthetic GND endpoint is removed or correctly connected, and a fresh full DRC reports no blocking errors.
Board outline and stackup
  • Board outline: 60.0 mm × 80.0 mm, rectangular with 3.0 mm corner radius.
  • Nominal finished thickness: approximately 1.30 mm.
  • Copper: 35 µm / 1 oz on all four layers.
  • Standard via: 0.60 mm pad / 0.30 mm finished drill.

Table


OrderLayerType / purposeMaterial / thickness
1Top solder maskMask0.025 mm, εr 4
2Top copperComponents and primary signals0.035 mm Cu
3Dielectric 1 + 2Top-to-L2 prepreg0.130 + 0.130 mm FR-4, εr ≈ 4.3
4Inner 1Continuous solid GND reference plane0.035 mm Cu
5Dielectric 3Core0.711 mm FR-4, εr ≈ 4.8
6Inner 2Power plane0.035 mm Cu
7Dielectric 4 + 5L3-to-bottom prepreg0.130 + 0.130 mm FR-4, εr ≈ 4.3
8Bottom copperSecondary signals0.035 mm Cu
9Bottom solder maskMask0.025 mm, εr 4
Keep Inner 1 unbroken beneath RF, USB, clocks, UART, and audio signals. Do not route a critical signal across a void or split in its reference plane.
Impedance and routing targets
Cellular and GNSS RF
  • Nets: CELL_RF and GNSS_RF from U7 to the two u.FL connectors.
  • Target: 50 Ω single-ended.
  • Route on top copper over the uninterrupted Inner-1 GND plane.
  • Provisional geometry in the current design: 0.30 mm microstrip over approximately 0.26 mm FR-4, εr ≈ 4.3.
  • No layer changes or signal vias unless unavoidable. Maintain a clear RF corridor, keep copper pours/components away according to the selected coplanar/microstrip geometry, and add nearby GND stitching outside the controlled clearance boundary.
  • Preserve the existing u.FL RF routes if importing routed geometry. They were deliberately excluded from all later rip-up operations.
  • Fabricator field-solver confirmation is mandatory. Provide the final material stack, copper thickness, solder mask, and 50 Ω target to the board fabricator and update the width/clearance to its calculated value before release.
USB 2.0
  • Nets: USB_D+ and USB_D−.
  • Target: 90 Ω differential.
  • Route as a coupled pair over continuous GND, preferably on top only, with minimal or no vias.
  • Provisional geometry: approximately 0.15 mm trace / 0.15 mm gap; replace with the fabricator's field-solved geometry.
  • Match intra-pair length within 0.5 mm and preserve symmetric pad escapes. Avoid stubs at the duplicated connector pads.
General rules
  • Minimum copper clearance: 0.20 mm.
  • Minimum trace width: 0.20 mm.
  • Preferred general signal width: 0.25 mm.
  • Preferred power width: 0.50 mm; minimum power width 0.30 mm where geometry forces a neck-down.
  • Use wide pours/traces and multiple vias for battery, charger, 3V3, and modem power. A single 0.30 mm via is not an adequate 2 A modem-current transition.
Critical nets and placement/routing intent

Table


Net / groupWhy it mattersHandoff requirement
MODEM_VBAT / U7 VBAT pins 55, 56, 57LTE transmit bursts demand a low-impedance source and the modem recommended range is 3.4–4.2 V.Implement one of the power options below. Place ≥100 µF bulk plus 10 pF, 33 nF, 100 nF, and 1 µF ceramics immediately beside the three VBAT pads. Use a short, wide feed; target at least 2 mm copper width or a plane/pour of equivalent impedance.
CELL_RF, GNSS_RFRF loss and mismatch directly reduce cellular/GNSS performance.50 Ω, top layer, no plane breaks, shortest practical path, no unapproved vias. Keep noisy switch nodes and class-D output away.
5V_IN / USB-C VBUS / U1 INFeeds the linear charger; carries connector current and has unresolved duplicate USB-C pads.Join all four USB-C VBUS pads locally with solid copper, then route a wide feed to U1 IN and its input capacitor. Avoid daisy-chaining through a narrow pad neck.
VBAT_CELLCarries charge current and modem/system burst current if direct-BAT architecture is selected.Join both U1 BAT pads with a local copper shape and place C2 adjacent. Use a low-resistance route to the cell connector; verify the cell protection board and connector for 2 A bursts.
USB_D+, USB_D−USB 2.0 signal integrity and enumeration.90 Ω differential, matched escape, continuous L2 reference, no stubs, ESD array at the connector recommended.
MODEM_UART_RX_3V3, corresponding UART TXRequired modem control/data path; U4 fine-pitch escape is currently blocked.Preserve TXB0104 only for UART translation. Route away from RF and class-D outputs; one signal via is acceptable if a nearby GND return via is provided.
PWRKEY, RESETMust function from the fully powered-off modem state.Do not route through U4. Implement the NPN open-collector circuits below. Keep collectors close to U7 and give each base a defined off state.
SPK_P, SPK_NHigh-edge-rate class-D currents can couple into mic/I2S/RF.Route as a tight differential-like pair from U5 to the speaker JST. Keep away from the five-pin microphone connector and its BCLK/WS/DATA traces. Do not reference either output to GND.
I2S microphone BCLK, WS, DATADigital microphone clock/data integrity; off-board cable increases emissions and susceptibility.Route together to the five-pin JST with GND adjacent in the connector pinout where possible. Keep clear of MAX98357A outputs and switch nodes; add ESD/series damping provisions if the cable is long.
ESP32 antenna areaCopper/components near the module antenna detune Wi-Fi/BLE.Preserve the module manufacturer's complete antenna keepout on every copper layer and avoid enclosure metal/battery overlap above or below it.
GNDReturn integrity for RF, USB, switching power, audio, and modem bursts.Use Inner 1 as an uninterrupted plane. Remove the stale synthetic stitch endpoint; add intentional stitching only after signal/power routing is stable.
Mandatory schematic fixes before final placement/routing
1. Correct modem supply
U7 VBAT pins 55, 56, and 57 must be removed from BQ24074 OUT / VSYS_BAT, which can be 4.3–4.5 V. The final U7 supply must never exceed the modem's 4.20 V recommended maximum.
2. Independent open-collector controls
  • PWRKEY: ESP32-S3 GPIO21 → nominal 10 kΩ base resistor → MMBT3904-class NPN base. Emitter to GND; collector to U7 PWRKEY pin 1. Optional 100 kΩ base-emitter pulldown. Driving GPIO21 high pulls PWRKEY low.
  • RESET: ESP32-S3 GPIO14 → nominal 10 kΩ base resistor → second NPN base. Emitter to GND; collector to U7 RESET pin 16. Optional 100 kΩ base-emitter pulldown. Driving GPIO14 high pulls RESET low.
  • Remove PWRKEY and RESET from U4 TXB0104.
  • Retain U4 only for U7's 1.8 V UART: U7 MAIN_UART_TXD pin 9 and RXD pin 10. U4 VCCA is supplied from U7 VDD_EXT pin 15, VCCB from 3V3, and OE must default low until both voltage domains are valid.
MODEM_VBAT architecture options
Option A — Dedicated regulated rail — compliant recommendation
Add a synchronous buck-boost or another regulator capable of the LTE burst load between the cell/system source and U7.
  • Target approximately 3.8–3.9 V nominal.
  • Select the regulator and feedback network so the calculated static maximum is no more than 4.05 V, leaving 150 mV for startup/load-release overshoot.
  • The measured and calculated worst case at U7 must be ≤4.20 V, including reference tolerance, divider tolerance, line/load regulation, startup, and overshoot.
  • Prefer an enable pin under MCU control to allow a true modem hard power cycle after an orderly shutdown.
Advantages: compliant voltage ceiling; stable modem voltage across cell state-of-charge; controlled power-cycle capability; some isolation from charger and audio/system disturbances.
Trade-offs: extra cost, area, EMI, quiescent current, conversion loss, and thermal/layout difficulty. The converter and inductor must tolerate 2 A-class burst current without saturation or loop instability, and the switch node must be kept away from RF and audio.
Option B — Direct BQ24074 BAT/cell feed — simpler but not strictly compliant
Connect U7 VBAT directly to the charger BAT node and permanently fitted cell, not to charger OUT.
Advantages: minimal parts and area; high efficiency; the battery naturally supplies transmit peaks; BQ24074's recommended BAT discharge rating is 4.5 A, so the charger BAT path itself can support a 2 A burst when the cell, protection PCB, connector, and copper are also rated for it.
Trade-offs and risks:
  • BQ24074 battery regulation is 4.20 V typical / 4.23 V maximum. Worst-case DC voltage is therefore 4.23 V before transient overshoot, which exceeds the modem's 4.20 V recommended maximum by 30 mV.
  • Voltage follows the cell. Near empty charge, cell droop plus path resistance can push U7 below 3.4 V during a transmit burst.
  • Modem current at BAT can disturb charge termination/recharge detection and increases cell cycling while USB is present.
  • No regulator enable is available for a true hard modem power cycle; the modem remains physically battery-connected while logically off.
Use this option only if the strict 4.20 V ceiling is explicitly relaxed and the complete battery path is validated at high and low state-of-charge. Otherwise use Option A.
Exact blocked-no-path geometry from prior attempts
These are physical escape/placement problems, not missing schematic connectivity.
U1 BQ24074 charger area
  • Current project placement record: U1 near (19 mm, −36 mm) in the layout coordinate frame.
  • The compact charger footprint places duplicate BAT_2/BAT_3, IN, OUT, GND/exposed-pad, and programming pins in a dense field.
  • Previous routes/vias occupied the only legal exits from IN and BAT. Fragmented legacy copper then left short isolated segments inside the escape corridor.
  • The router could see U1 IN/BAT endpoints but found no clearance-compliant path around the exposed-pad/GND region and adjacent fine pads.
  • Correction in the destination tool: delete all old copper around U1 before routing. Create local same-net copper shapes joining duplicate BAT pads and, where applicable, duplicate power pads. Place C1 immediately at IN–GND and C2 immediately at BAT–GND. Rotate or move U1 and its programming resistors as a block if the IN/BAT exits cannot each obtain a direct wide corridor. Do not attempt to patch isolated legacy segments.
U4 TXB0104 level shifter area
  • Current project placement record: U4 near (−3 mm, 2 mm) in the layout coordinate frame.
  • Fine-pitch A-side/B-side pads, VCCA, VCCB, OE, and GND had no clean fanout corridor after nearby traces and vias were placed.
  • The unresolved MODEM_UART_RX_3V3 route is specifically U3 IO18 ↔ U4 B2.
  • The old four-channel assignment also routed PWRKEY and RESET through U4, consuming escape capacity and creating the startup defect.
  • Correction: first remove the two control channels from U4. Re-place U4 so its B-side faces the ESP32 and its A-side faces U7. Place one 100 nF capacitor at each supply pin with direct GND vias. Fan out U4 pads before routing surrounding nets; permit a single layer transition for UART if necessary, with a nearby GND via.
J7 USB-C VBUS area
  • Current project placement record: J7 near (−24.8 mm, 28 mm), rotated 270°, using the TYPE-C-2 footprint.
  • VBUS pads A4, A9, B4, and B9 are one schematic net but were represented as multiple physical islands. Two current airwires remain between those duplicate pads.
  • The connector pad field and prior fine-pad copper left no legal path for the router to join all four VBUS pads and escape toward U1.
  • Correction: verify the destination footprint maps all four pads to the same net. Join A4/A9/B4/B9 immediately behind the receptacle with a broad local 5V copper shape, then leave the connector through one wide neck toward the input capacitor/charger. Do not make the global router join the four pads individually. Preserve the USB D+/D− escape symmetry and avoid a VBUS pour that intrudes into the differential-pair corridor.
Current outstanding DRC and connectivity
Latest live DRC: 8 airwire errors, 0 dangling traces. The current filtered DRC returned no additional open floating-copper, overlapping-copper, overlapping-trace, under-connected-via, outside-board, body-overlap, stackup, or pad-access checks. Run a complete destination-tool DRC after import because rule translation may reveal additional clearance, mask, courtyard, and fabrication violations.

Table


DRC labelCanonical netUnconnected endpoints / meaningRequired action
Trace a1895V_INLegacy local connection toward U1 IN / C1 / 5 V branch.Delete the legacy segment and rebuild the entire J7/J1-to-C1/U1-IN feed as wide copper.
VBUS #15V_INOne disconnected group among J7 A4/A9/B4/B9.Join all four VBUS pads locally.
VBUS #25V_INSecond disconnected group among J7 A4/A9/B4/B9.Same local VBUS copper solution; confirm no duplicate-pad footprint defect remains.
15V_INJ1 pin 1 to the charger/input network, principally U1 IN and C1 P1.Route a wide, fused/protected input path as required by the final connector architecture.
P1SIM_VDD_MODEMR11 P1 to C18 P1, C19 P1, and U7 SIM_VDD.Rebuild the short local SIM supply route; review whether R11 should remain because the modem reference does not show a series resistor in SIM_VDD.
BAT_3VBAT_CELLU1 BAT_3 to U1 BAT_2, J2 pin 1, and C2 P1.Join duplicate U1 BAT pads locally and route a wide battery path.
IO18MODEM_UART_RX_3V3U3 IO18 to U4 B2.Re-place/fan out U4 and route from clean endpoints.
c637d7bf / stitch.49GNDStale virtual/synthetic GND stitch endpoint to a GND pad.Delete the synthetic stitch object or replace it with an intentional plated GND via connected to the L2 plane.
Airwires grouped by canonical net
  • 5V_IN: 4 — Trace a189, two J7 VBUS links, and J1 pad 1.
  • SIM_VDD_MODEM: 1 — P1.
  • VBAT_CELL: 1 — BAT_3.
  • MODEM_UART_RX_3V3: 1 — IO18.
  • GND: 1 — synthetic stitch.49 endpoint.
  1. Import schematic and board; verify U7 is the complete 124-pad, 24 × 24 mm, 1.0 mm-pitch footprint and pin 1 orientation matches the physical module marking.
  2. Implement the mandatory MODEM_VBAT, PWRKEY, and RESET schematic changes; update PCB from schematic.
  3. Select the MODEM_VBAT architecture. If regulated, place the converter, inductor, input/output capacitors, enable network, and U7 bulk capacitors as one compact power block before routing.
  4. Replace or repair the USB-C footprint so all duplicated VBUS/GND/D+/D− pads map correctly.
  5. Remove all stale copper and synthetic stitch objects on the eight unresolved connections. Do not preserve fragmented legacy routes.
  6. Re-place U1 and U4 functional groups to provide direct pad escapes as described above.
  7. Lock U7, both u.FL connectors, RF routes, ESP32 antenna keepout, USB-C, and edge connectors.
  8. Route RF and USB first using fabricator-confirmed impedance geometry.
  9. Route modem/battery/charger power with wide copper and parallel vias, followed by UART/I2S/GPIO.
  10. Route MAX98357A outputs last while maintaining separation from the microphone connector and RF paths.
  11. Add intentional GND stitching, maintaining RF controlled-clearance and antenna keepout.
  12. Run ERC, full DRC, unconnected-pad check, impedance review, plane-return review, and assembly/BOM validation. Release only with zero airwires and zero unconnected pads.
Manufacturing handoff gate
Before Gerber/ODB++, Excellon, BOM, CPL, or STEP release, confirm:
  • All eight listed airwires are gone and no new airwires exist.
  • No dangling, floating, duplicate, or overlapping copper remains.
  • Both u.FL routes meet the fabricator-confirmed 50 Ω geometry.
  • USB pair meets the confirmed 90 Ω differential geometry and length tolerance.
  • ESP32 antenna keepout is clear on every copper and component layer.
  • MODEM_VBAT is validated across charging, USB present/absent, battery high/low, modem startup, transmit burst, and load release.
  • U7 PWRKEY and RESET operate while U7 VDD_EXT is absent.
  • All BOM lines have valid manufacturer and LCSC order codes, and CPL rotations/origins are checked against assembly drawings.
  • Purpose and release status

  • Board outline and stackup

  • Impedance and routing targets

  • Cellular and GNSS RF

  • USB 2.0

  • General rules

  • Critical nets and placement/routing intent

  • Mandatory schematic fixes before final placement/routing

  • 1. Correct modem supply

  • 2. Independent open-collector controls

  • MODEM_VBAT architecture options

  • Option A — Dedicated regulated rail — compliant recommendation

  • Option B — Direct BQ24074 BAT/cell feed — simpler but not strictly compliant

  • Exact blocked-no-path geometry from prior attempts

  • U1 BQ24074 charger area

  • U4 TXB0104 level shifter area

  • J7 USB-C VBUS area

  • Current outstanding DRC and connectivity

  • Airwires grouped by canonical net

  • Recommended completion sequence in the destination tool

  • Manufacturing handoff gate