JLCPCB Shortfall Replacement Guide Decision summary — 2026-10-15
This is sourcing advice for the seven entries in the uploaded shortfall list, not an updated BOM or fabrication approval. No schematic, footprint, routing, or BOM properties were changed. Stock observations are point-in-time public catalog/distributor results, not a reservation in your JLCPCB order; checkout availability wins. LCSC stock is explicitly distinguished from JLCPCB assembly stock below.
What to select for each item
The requested purchase quantities come from the user's pasted order screen, not a new assembly quantity calculation. JLCPCB may require additional pieces for assembly attrition. Keep any required extra quantity when rematching.
Why U1's suffix swap is safe
I saved the seven-part replacement list—with exact LCSC numbers, stock checks, and unresolved qualifications—in your project files: JLCPCB Shortfall Replacement Guide; the immediately stocked recommendations are R2 → C346633 and R3 → C2684521.
The guide gives exact alternatives for the feedback resistor and charger pending checkout availability, a conditional capacitor candidate, and recommends sourcing the original inductor and modem rather than an unverified swap; I haven’t changed your BOM or board.
Before releasing the order, request a fresh DRC/connectivity check: your latest saved checkpoint still flags copper overlaps and unrouted USB connections.
U6 and L2 not letting me to source
I’ll check alternatives for those two parts and JLCPCB’s sourcing restrictions; I won’t assume pre-ordering is available for your order.
My earlier pre-order suggestion wasn’t a confirmed purchasing route for your order, and I haven’t verified a safe, stocked drop-in for U6 or L2. JLCPCB distinguishes stock shortages, sourcing restrictions, and “Standard Only” assembly restrictions, so the exact message matters.
Can you share a screenshot of what appears when you try sourcing each part, and whether your order uses Economic or Standard assembly?

Waiting for input


Modem Power Startup Diagnosis
Conclusion
Low voltage at U6 does not, by itself, establish that U7 is damaged. No bench measurements have been supplied. The current design has a definite startup dependency to investigate, an upstream USB-only current limitation, and previously documented U7 assembly risks. No schematic or layout changes were made during this diagnosis.
Current schematic findings
  • U7 is LTC3113EDHD#TRPBF. VIN pins 3–5 connect to VSYS_BAT; VOUT pins 1–2 connect to MODEM_3V8; L2 connects SW1 to SW2; SGND and the exposed pad connect to GND. These pin assignments agree with the manufacturer pinout. The exposed pad is PGND and must be soldered to the PCB.
  • R32 = 0 ohms straps RUN to VSYS_BAT. The regulator does not require firmware enable. RUN below 0.3 V shuts it down; above 1.2 V enables it.
  • R27 = 845 kohms from output to FB and R28 = 158 kohms from FB to GND. Using VOUT = 0.600 × (1 + R2/R1) V gives a calculated nominal output of approximately 3.809 V. This is a schematic calculation, not a measurement or verification of loaded regulation.
  • U6 VBAT pins 55–57 connect to MODEM_3V8. U6 VBUS pin 24 instead connects to 5V_IN. Do not confuse USB VBUS with the modem's main supply.
Startup dependency: U4 may block the power-key command
U3 GPIO21 reaches U6 PWRKEY only through U4 channel B3/A3. U4 VCCA and OE both connect to MODEM_1V8, generated by U6 VDD_EXT. If MODEM_1V8 is absent before U6 starts, U4 cannot pass the ESP32 power-key command: TXB0104 places all outputs in high impedance when VCCA is at ground.
This wiring dependency is confirmed. Whether it is the failure on the physical board depends on measuring MODEM_1V8 before the attempted start. Zero volts on MODEM_1V8 alone is not proof of inadequate VBAT. A future correction would use an independently powered open-drain/transistor control for PWRKEY, after confirming the exact modem control specifications. Do not bypass U4 by applying 3.3 V directly to modem signal pins.
USB-only supply limitation
U1 is BQ24074; EN2 is strapped to VSYS_BAT and EN1 to GND, selecting resistor-programmed input current limit once powered. R2 is 1.18 kohms. With IIN-MAX = KILIM/RILIM and typical KILIM = 1610 Aohms, the calculated typical input limit is approximately 1.364 A, shared by system load and charging.
A battery can supplement system load once charger current has been reduced to zero and the system exceeds the input limit.
Consequently, adding a downstream buck-boost regulator does not guarantee USB-only full-power modem operation. This does not establish that the limit is preventing initial turn-on; input/output voltage measurements during startup are needed. The project target of approximately 2 A RF bursts is a design requirement, not a newly verified SIM7670G peak-current specification.
Existing assembly risk
The prior U5/U7 reflow and paste audit documented one large, unsplit, full-area U7 exposed-pad paste aperture and substantial solid-ground copper attachment. These are assembly risk findings, not evidence that this particular board has a failed joint. If input and enable are healthy but output is low, inspect U7 perimeter joints, exposed-pad soldering, R27/R28, R32 and L2 before replacing the IC.
Measurements to send
Use GND as the reference. Prefer accessible capacitor/resistor pads over tiny IC pins; avoid shorting neighboring pads with the probe. Record idle voltage and voltage during the attempted modem start. A scope is needed to capture brief dips that a multimeter can miss.

Table


MeasurementAccessible locationDiagnostic purpose
VSYS_BATC21 positive pad, near U7Confirms regulator input supply; watch for collapse during startup
U7_RUNR32 side connected to RUNShould follow VSYS_BAT through the 0-ohm strap; above 1.2 V enables U7
MODEM_3V8 near U7C23 positive padExpected approximately 3.81 V from fitted divider
MODEM_3V8 near U6C15 positive padCompare with output near U7 to reveal a route/joint voltage drop
MODEM_1V8C10 positive padDetermine whether U4 has its low-voltage supply before PWRKEY
U7_FB, optionalR28 side connected to FBNominal 0.600 V during forced-PWM regulation; avoid loading this node
Interpretation:
  1. VSYS_BAT falls during start: investigate upstream USB adapter/cable, U1 current limit, battery and connections first.
  2. VSYS_BAT is healthy but RUN is low: investigate R32 and its solder joints/routing.
  3. Input and RUN are healthy but output at U7 is low: investigate output shorts, U7 assembly, L2, feedback and converter operation. This still does not prove IC damage.
  4. Output near U7 is good but near U6 is low: investigate the interconnecting copper and solder joints.
  5. MODEM_3V8 is correct but MODEM_1V8 remains absent and PWRKEY never goes low: investigate the startup dependency before UART firmware.
Do not inject an external supply into MODEM_3V8 without first planning isolation from U7. Do not connect USB 5 V directly to modem VBAT. Remove USB and battery before resistance/continuity checks.
Evidence limitations
The datasheet attached to U6 identifies itself as SIM7672X Series Hardware Design V1.01, not explicitly SIM7670G-MNGV. Its numeric peak-current entry is TBD, so it cannot substantiate an exact SIM7670G peak-current claim.
A web search found a SIM7670G HAT reference schematic and related family documents, but not a verified exact-part hardware specification sufficient to prescribe a bench PWRKEY pulse. Exact SIM7670G-MNGV cold-start VDD_EXT availability and control timing remain unverified; no manual shorting or timing experiment is prescribed here. U7's stored datasheet URL points to an ISO certificate, so this diagnosis used the manufacturer LTC3113 datasheet instead.
The physically assembled revision must match the current schematic for these probe locations and circuit interpretations to apply. Other ongoing work may change the live design; this file records the state inspected on October 6, 2026.
  • Conclusion

  • Current schematic findings

  • Startup dependency: U4 may block the power-key command

  • USB-only supply limitation

  • Existing assembly risk

  • Measurements to send

  • Evidence limitations