MILSPEC Continuity Tester


Created a thread
38999 Cable Tester
Needs input
View Thread
I stopped PCB work and audited the schematic baseline: it currently contains 95 components, 164 nets, and no open ERC findings as of the latest check. A dedicated executor completed a deeper pin-level audit/correction pass, but I could not retrieve or independently verify its report or applied changes.
Still required
  • Reconcile the executor’s schematic changes.
  • Verify scan coverage, hit capture, MULTIPLE logic, NEXT behavior, display conversion, reset behavior, and unused CMOS inputs.
  • Run a fresh ERC and independent logic review.
  • Keep PCB placement/routing paused until those checks pass.
Execution stopped because your ACUs ran out.
Received notification from "38999 Cable Tester" that it finished — picking the work back up.
The “38999 Cable Tester” executor reports completion, but I could not access its detailed report, inspect the resulting schematic, or reconcile its changes against the outstanding functional checks. No additional project changes were made in this turn.
Still required before PCB work resumes:
  • Verify all 55 contacts are scanned exactly once.
  • Validate hit capture, MULTIPLE indication, and NEXT-button sequencing.
  • Check displayed contact-number conversion and reset/startup behavior.
  • Confirm unused CMOS inputs are tied to defined logic levels.
  • Run fresh ERC/connectivity checks and an independent schematic review.
Execution stopped because your ACUs ran out.
Review tester schematic
Check contact coverage
Review sequencing logic
Check CMOS inputs
Run electrical review

Waiting for input


Board Bring-Up Plan
1. Unpowered Checks
  1. Confirm no MCU, programmable logic, or programming connector is fitted.
  2. Verify resistance from protected +5 V to GND is not a short.
  3. Check USB-C CC1-to-GND and CC2-to-GND are each approximately 5.1 kΩ.
  4. Verify J2/J3/J4 continuity maps exactly to C01–C55 and no adjacent header pins are shorted.
  5. Verify PROBE_RETURN reaches the probe connector through 470 Ω.
2. Power Checks
  1. Power from a current-limited 5 V bench source first; set a 200 mA limit.
  2. Confirm protected +5 V after F1 is within the logic operating range.
  3. Check each IC supply pin and verify no device heats abnormally.
  4. Confirm RESET_N starts low and rises after the RC delay.
3. Clock and Address Checks
  1. Probe OSC_RAW and SCAN_CLK; expect a stable oscillator near 6 kHz, with tolerance allowed.
  2. Verify U1 ones BCD counts 0–9 and U2 tens increments on ones rollover.
  3. Confirm the recurring operational sequence is 01 through 55, then 01; 56–99 must never appear.
  4. Confirm U9 enables only one mux bank at a time.
4. Continuity Threshold Checks
  1. With no contact connected, SENSE must be HIGH and HIT LOW.
  2. Connect the probe return to C01 through 0 Ω, 100 Ω, and then a higher resistance decade box.
  3. Verify C01 produces HIT reliably at 100 Ω across repeated scans.
  4. Test C09/C10, C19/C20, C29/C30, C39/C40, C49/C50, and C55 to cover every bank boundary.
  5. Verify unused mux channels never produce a displayed address.
5. Display Checks
  1. With no hit, both digits must be blank.
  2. Apply one hit at each decade boundary and verify decimal display: 01, 09, 10, 19, 20, 29, 30, 39, 40, 49, 50, 55.
  3. Measure segment current and confirm acceptable brightness and CD4511 output voltage.
6. NEXT Checks
  1. Apply hits at C03, C17, and C55.
  2. Starting from 03, press NEXT and verify 17, then 55, then wrap to 03.
  3. Hold NEXT briefly and confirm only one search is armed after release.
  4. Remove the displayed contact and verify the display blanks briefly then acquires another live hit.
  5. With only one live hit, press NEXT and verify the same address returns after one wrapped search.
7. MULTIPLE Checks
  1. Apply no hits: MULTIPLE must clear after one complete frame.
  2. Apply one hit: MULTIPLE must remain clear.
  3. Apply two hits, including adjacent addresses: MULTIPLE must assert after the frame completes.
  4. Remove one of two hits: MULTIPLE must clear after the next completed frame.
  5. Include C55 as the second hit to verify end-of-frame sampling.
Pass Criteria
The board passes when it continuously scans 01–55, detects a 100 Ω remote path on every channel, displays the selected decimal address, cycles through live hits with NEXT including wrap, blanks with no hits, and updates MULTIPLE solely from the most recently completed frame without resets, lockups, or false addresses.
  • 1. Unpowered Checks

  • 2. Power Checks

  • 3. Clock and Address Checks

  • 4. Continuity Threshold Checks

  • 5. Display Checks

  • 6. NEXT Checks

  • 7. MULTIPLE Checks

  • Pass Criteria